Royale 报告二叠系密西西比系层段取得良好成果

Royale Energy 拥有四口生产井,其中第五口和第六口正在德克萨斯州埃克托县钻探并完成,计划于今年晚些时候上线。

哈特能源员工

Royale Energy 5 月 30 日更新了二叠纪盆地密西西比段四口井的进展情况,并表示德克萨斯州埃克托县还有两口井正在完成。

该公司是与Ares Ltd联合开发协议的一部分。Royale 表示,Ector 净面积 17,000 英亩的项目中的第五口和第六口井正在钻探和完成。

第五口井于 2 月份开始钻探,预计将于 2024 年第二季度末投产。该井目前处于完井液回流的早期阶段,目前日产量超过 700 桶和 850,000 立方英尺。

第六口井于 5 月开始钻探,预计将于 2024 年第二季度末或第三季度初达产。

Royale 表示,最近还收到了二叠纪盆地一家未透露姓名的大型石油公司提出的收购该项目所有权的要约,但该公司拒绝了这一要约。 Royale 及其投资者拥有位于德克萨斯州埃克托县的第五口井和第六口井 5% 的工作权益。

Royale首席执行官约翰尼·乔丹表示,该公司预计今年将再钻两口井,到2024年该项目将总共钻四口井。

“随着我们今年持续开发活动的贡献,该项目令人兴奋的潜力将变得更加明显,”乔丹说。

原文链接/HartEnergy

Royale Reports Favorable Results in Permian’s Mississippian Interval

Royale Energy has four producing wells, with a fifth and sixth being drilled and completed in Ector County, Texas, with plans to bring them online later this year.

Hart Energy Staff

Royale Energy updated on May 30 progress made on four wells in the Mississippian interval of the Permian Basin and said two more are in the process of being completed in Ector County, Texas.

The company is part of a joint development agreement with Ares Ltd. Royale said a fifth and sixth well are in the process of being drilled and completed on a 17,000 net acre project in Ector.

The fifth well, which began drilling in February, is expected to be reach production late in the second quarter of 2024. The well is currently in the early stages of flowing back completion fluids is currently producing over 700 bbl/d and 850,000 cf/d.

The sixth well began drilling in May and is expected to reach production in the late second or early third quarter of 2024.

Royale also recently received an offer from an unnamed major oil company in the Permian to purchase its ownership in this project, but declined the offer, the company said. Royale and its investors have a 5% working interest in the fifth and sixth wells, which are located in Ector County, Texas.

Royale CEO Johnny Jordan said the company anticipates drilling two more wells this year for a total of four wells on the project in 2024.

“The exciting potential of this project will become more evident with the contribution from our continued development activity over the course of this year,” Jordan said.