Touchstone Exploration公布Carapal Ridge-3钻探结果

来源:www.gulfoilandgas.com,2026年1月5日,地点:南美洲

Touchstone Exploration Inc.(简称“Touchstone”)(多伦多证券交易所、伦敦证券交易所代码:TXP)发布位于特立尼达和多巴哥共和国陆上中央区块的Carapal Ridge-3开发井(简称“CR-3”)的最新作业进展。Touchstone持有该井65%的作业权益,Heritage Petroleum Company Limited持有剩余的35%。

主要亮点
:- CR-3是过去17年来在Carapal Ridge油藏钻探的第一口井,钻遇约1082英尺净砂层,其中包括约1000英尺净Herrera砂层。-
裸眼测井、泥浆录井和钻井数据共同表明,Herrera层段存在含油气砂层。-
该井在多个Herrera层段(包括页岩标志层上下)均钻遇厚层油气藏。
- 完井作业正在进行中,预计将于2026年第一季度与中央区块天然气处理厂连接。-
该井的钻探结果支持在中央区块再钻探至多三口Herrera开发井。-
CR-3井还在Karamat地层发现了第二个井上含气层,目前正将其作为独立勘探目标进行评估。CR

-3井于2025年11月23日开钻,使用Star Valley钻机205号,历时35天钻至8200英尺的总深度。完成裸眼测井作业后,该井已下套管,为未来的生产做好准备。根据初步的现场成本估算,该井的成本超出预算约25%,但无需进行任何侧钻作业。额外的时间和成本主要归因于控制Karamat砂层天然气流量所需的工作,该砂层此前在中央区块尚未开采过。
了解更多
车辆电子系统
燃料
汽车经销店
车辆
船运
丰田
充电点
直流充电
电动汽车


CR-3井的主要目标是卡拉帕尔岭油藏中普遍存在的埃雷拉砂层。CR-3井是过去17年来在卡拉帕尔岭油藏钻探的第一口井,钻遇了约1000英尺厚的埃雷拉砂层。该井的目标是位于30英尺页岩层标志层上方、目前正在生产的已开发储层段内的埃雷拉砂层,以及页岩层标志层下方的未生产埃雷拉砂层。下部砂层此前已由前一家作业者在邻近的卡拉帕尔岭-1井中完成完井测试,但并未进行生产。这些完井测试,即4号、5号和6号测试,在约一到两天的时间内,平均每日峰值产量合计超过2000万立方英尺天然气和500桶凝析油。

CR-3井在已开发的埃雷拉(Herrera)油藏中,于页岩标志层上方6930英尺至7770英尺深度处钻遇约635英尺的净砂层;在未开采油藏中,于页岩标志层下方7770英尺至8200英尺深度处钻遇约365英尺的净埃雷拉砂层。尽管钻井在8200英尺处终止,但该井在整个深度范围内均处于纯净砂层中。除埃雷拉砂层外,在埃雷拉地层正上方6530英尺至6760英尺深度处还钻遇约82英尺的净卡拉马特(Karamat)砂层。这些卡拉马特砂层也存在于卡拉帕尔岭-1井和卡拉帕尔岭-2井中。

该井最初计划为一口以埃雷拉砂层为目标的斜井;然而,在钻井过程中,生产段井眼自然形成倾斜角,水平钻进约341英尺进入未开采的埃雷拉砂层,从而优化了储层暴露。裸眼测井、泥浆录井和钻井数据共同表明,埃雷拉层段存在含油气砂层,并延伸至水平段末端。
了解更多
直流充电
充电点
电池
充电点
货物
船运
电池
车辆
车辆
丰田


CR-3井的完井作业正在进行中。公司计划先从页岩标志层以下的水平井段开采未开发的Herrera砂层,而井上已开发的Herrera砂层可能会在以后进行射孔。 CR-3井的大部分连接设备已采购完毕,目前运抵特立尼达,预计将于2026年第一季度与中央区块天然气处理厂完成连接。

总裁兼首席执行官Paul R. Baay评论道:
“CR-3井是我们中央区块的首口开发井,也是该油田17年来钻探的第一口井。我们的钻井团队成功完成了该井的钻探,这也是我们首次钻探至埃雷拉油藏的水平井。正如预期

,CR-3井在关键页岩标志层上下均发现了含油砂层。我们计划首先从井的下部水平段进行生产,井上段的大量砂层可用于未来的射孔作业。虽然该井在多个层位发现了厚层的含油层,但最终的产能要等到完井并接入处理厂后才能确定。影响产能的因素有很多,包括该地层此前从未进行过水平井生产以及井下作业的管理等。”压力方面,

重要的是,该井证实了地震模型以及厚层埃雷拉地层的分布范围。这些结果令人鼓舞,并支持在该区块再钻探三口埃雷拉井。该井还在卡拉马特组约6700英尺处发现了第二个含气层,目前正在评估其作为独立勘探目标的未来钻探前景。我们期待在本季度将CR-3井接入我们的中央区块设施,以提高我们在两项液化天然气销售协议下的天然气销量和实际售价。

测井、射孔、测试 >>

特立尼达和多巴哥测井、射孔、测试新闻 >>



加拿大 >> 2025年12月15日 - Bonterra Energy Corp.(简称“Bonterra”或“公司”)欣然宣布其最新的Charlie Lake油井勘探结果,以及一项对Charlie Lake油田的战略性收购……
蒙古 >> 2025年12月12日 - 在伦敦证券交易所创业板上市的蒙古石油公司Petro Matad Limited欣然发布以下运营更新。

主要更新

包括:……


了解更多
电动汽车
车辆
电池
丰田C-HR
纽约证券交易所
电池充电器
丰田
电池
汽车的



原文链接/GulfOilandGas

Touchstone Exploration Announces Carapal Ridge-3 Drilling Results

Source: www.gulfoilandgas.com 1/5/2026, Location: South America

Touchstone Exploration Inc. ("Touchstone") (TSX, LSE: TXP) provides an operational update on the Carapal Ridge-3 development well ("CR-3"), located on the Central block onshore in the Republic of Trinidad and Tobago. Touchstone holds a 65 percent operating working interest in the well, with Heritage Petroleum Company Limited holding the remaining 35 percent.

Highlights
- CR-3 is the first well drilled into the Carapal Ridge pool in the past 17 years and encountered approximately 1,082 feet of net sand, including approximately 1,000 feet of net Herrera sand.
- Open-hole wireline logging, mud logging, and drilling data collectively indicate the presence of hydrocarbon-bearing sands throughout the Herrera interval.
- The well encountered a thick pay zone across multiple Herrera horizons, both above and below a shale marker.
- Completion operations are underway, with tie-in to the Central block natural gas processing facility targeted for the first quarter of 2026.
- The well results support the potential for up to three additional Herrera development wells on the Central block.
- CR-3 also established a second, uphole, gas-charged play in the Karamat formation, which is being evaluated as a stand-alone prospect for potential drilling.

The CR-3 well was spud on November 23, 2025, using Star Valley Drilling Rig #205 and was drilled to a total depth of 8,200 feet over a 35-day period. Following open-hole logging operations, the well was cased for future production. Based on initial field-level cost estimates, the well was approximately 25 percent over budget and did not require any sidetrack operations. The additional time and costs were primarily attributable to efforts required to control natural gas flows from the Karamat sands, which have not previously been produced on the Central block.
Discover more
Vehicle electronics
Fuels
Car dealership
Vehicles
shipping
Toyota
charging points
car
DC charging
electric vehicles


The primary target of the CR-3 well was the Herrera sands, which are prevalent within the Carapal Ridge pool. CR-3 is the first well drilled into the Carapal Ridge pool in the past 17 years and encountered approximately 1,000 feet of net Herrera sand. The well targeted Herrera sands within the developed reservoir section currently on production above a 30-foot shale marker, as well as unproduced Herrera sands below the shale marker. The lower sands were previously completed and tested, but not produced, by a prior operator in the offsetting Carapal Ridge-1 well. These completion tests, known as tests 4, 5 and 6, flow tested at combined peak average daily test rates of over 20 million cubic feet of natural gas and 500 barrels of condensate for periods of approximately one to two days.

CR-3 encountered approximately 635 feet of net sand in the developed Herrera reservoir at depths between 6,930 feet and 7,770 feet above the shale marker and approximately 365 feet of net Herrera sand below the shale marker within the unproduced reservoir at depths between 7,770 feet and 8,200 feet. Although drilling was terminated at 8,200 feet, the well remained within clean sand at total depth. In addition to the Herrera sands, approximately 82 feet of net Karamat sands were also encountered directly above the Herrara formation at depths between 6,530 feet and 6,760 feet. These Karamat sands are also present in the Carapal Ridge-1 and Carapal Ridge-2 wells.

The well was originally planned as a deviated well targeting the Herrera sands; however, during drilling, the well naturally built angle in the production section and approximately 341 feet was drilled horizontally into the unproduced Herrera sand package, optimizing reservoir exposure. Open-hole wireline logging, mud logging, and drilling data collectively indicate the presence of hydrocarbon-bearing sands throughout the Herrera interval, extending to and including the end of the horizontal section.
Discover more
DC charging
charging points
Battery
charging point
shipments
shipping
batteries
Vehicle
Vehicles
Toyota


Completion operations are underway at CR-3. The Company intends to initially produce the undeveloped Herrera sands from the horizontal section of the well below the shale marker, while the uphole developed Herrera sands may be perforated at a later date. Much of the CR-3 facility tie-in equipment has been procured and is currently in Trinidad, with tie-in to the Central block natural gas processing facility targeted for the first quarter of 2026.

Paul R. Baay, President and Chief Executive Officer, commented:
"The CR-3 well is our inaugural development well on the Central block and the first well drilled on the field in over 17 years. The well was executed successfully by our drilling team and represents our first horizontal well drilled into the Herrera reservoir.

As anticipated, CR-3 encountered hydrocarbon-bearing sands both below and above a key shale marker. We intend to initially produce from the lower horizontal section of the well, with significant volumes of uphole sands available for potential future perforation. While the well has resulted in thick pay zone across multiple horizons, the ultimate deliverability will not be known until the well is completed and tied into the facility. Several variables will influence performance, including the fact that the formation has not previously been produced from a horizontal well and the management of downhole pressures.

Importantly, the well has confirmed both the seismic model and the areal extent of a thick Herrera section. These results are encouraging and support the potential for three additional Herrera wells on the block. The well has also established a second gas-charged play in the Karamat formation at approximately 6,700 feet, which is now being evaluated as a stand-alone prospect for future drilling. We look forward to tying CR-3 into our Central block facility in the quarter to enhance our natural gas sales volumes and realized pricing under our two liquefied natural gas marketing arrangements."

Logging, Perforating, Testing >>

Logging, Perforating, Testing News in Trinidad and Tobago >>



Canada >>  12/15/2025 - Bonterra Energy Corp. (“Bonterra” or the “Company”) is pleased to announce its latest Charlie Lake well results, a strategic Charlie Lake acquisition ...
Mongolia >>  12/12/2025 - Petro Matad Limited, the AIM quoted Mongolian oil company, is pleased to provide the following operational update.

Key updates

·...


Discover more
Electric vehicle
vehicle
Car
Electric battery
Toyota C-HR
New York Stock Exchange
Battery charger
Toyota
batteries
car’s