Petro-Victory Energy 提供 Sao Joao 油田修井活动的最新信息

来源:www.gulfoilandgas.com 2/29/2024,地点:南美洲

Petro-Victory Energy Corp.(“Petro-Victory”)(多伦多证券交易所股票代码:VRY)很高兴提供有关修井活动的最新信息,该活动旨在提高位于 Maranh Barreirinhas 盆地 100% 拥有权的 S??o Jo?? 油田的石油产量巴西,茫茫。

亮点:
- SJ-01 在预算范围内提前完成,在 Tutoia 地层增加了 32.2 米的油层。
- SJ-01初始产量为每天303桶石油(“bopd”)。

- SJ-11 在预算范围内按计划成功完成,在 Tutoia 地层增加了 16 米的油层。
- SJ-11平均每天生产37桶,完井液仍在回收中。
- SJ-06修井提前开始,SPT-129修井机已就位。

SJ-01 井
2024 年 2 月 16 日,SPT-129 修井机从 SJ-11 井调动至 SJ-01 井,修井计划旨在在 Tutoia 地层的 5 个区域再开挖 32.2 米。

Petro-Victory 成功重新进入该井,深度达 1,963 米,并在之前开放和枯竭的 BGARP-E 区域上方安装了桥塞,该区域已开放和生产了 60 多年。随后,该团队在 5 个先前计划的区域中伐木并穿孔了原计划的 32.2 米。

该井于 2024 年 2 月 27 日在预算范围内提前完成,井上重新安装了 1 录英寸插入泵、气锚和 API-160 抽油机。SJ-01 井现在有 32.2 Tutoia 地层中打开了数米的产油层。开放区域是干净的砂岩,平均孔隙度为 21%。

修井后 SJ-01 井的初始产量的具体数据如下:

- SJ-01 井已打开2月28日,通过抽油机人工举升支撑与生产站连接。2月29日上午,该井开始自然排油,初始排量为303桶/天。

- SJ-01井的总探明(“1P”)石油储量为19.9万桶石油,总探明加概算(“2P”)石油储量为30.3万桶石油。

该团队继续监测井压、生产率、流体分离、完井液回收以及伴生气体水平。

初始生产结果并不一定代表长期绩效或最终恢复情况。

SJ-11 井
正如之前宣布的,SPT-129 修井机于 2024 年 1 月 25 日抵达并开始在 SJ-11 井进行修井作业,以在 Tutoia 地层的 6 个区域中打开并测试另外 21.8 米的井段。

Petro-Victory 成功重新进入井深 1,694 米,记录该井,随后在 1,400 米至 1,634 米深度之间的 5 个计划区域射孔 16 米,石油和伴生气显示证实了这是天然气驱动的预期、石油多产、地层。

Tutoia H 区是一个 6 米深的产油区,已开放并生产了 40 多年,在修井期间,该区和其他先前开放的区域总共吸收了 1,700 桶完井液,团队努力成功恢复循环与LCM代理商合作并充分完成工程计划。

该井于 2024 年 2 月 16 日在预算范围内按计划成功完成,井上重新安装了 1 录英寸插入泵、气锚和 API-160 抽油机。SJ-11 井现在有 45 米Tutoia 地层中开放的油层。开放区域是干净的砂岩。平均孔隙度为 20%。

修井后 SJ-11 井的初始产量具体数据如下:
- SJ-11 井平均产量 37 桶过去 7 天每天生产液体,在最初的 60 小时测试中每天生产 37.5 桶液体,定期增加至每天 150 桶液体,现在每天生产 32.7 桶液体过去 48 小时定期增加至每天 108 桶流体。
- 自完井以来,SJ-11 井产出了 350 桶流体和伴生气。迄今为止,该井已产出 306 桶石油。
- 石油来自Tutoia地层的是一种轻质原油,20摄氏度时API比重为39.8°。
- 初始产量显示完井液为 100%,并转向满产油(完井液为 0%),过去 48 小时内平均产油量为 83%。
- 估计还有 1,656 桶完井液有待回收。

SJ-11井的总探明储量(“1P”)为20万桶石油,总探明加概算储量(“2P”)为45.8万桶石油。

该团队继续监测井压、完井液回收率以及伴生气体水平。为了有效管理水库,抽油机目前以最佳泵频率运行,并使用 64/64 节流阀尺寸。

初始生产结果并不一定代表长期绩效或最终恢复情况。

SJ-06 井
2024 年 2 月 27 日,SPT-129 修井机从 SJ-01 井调至 SJ-06 井,修井计划旨在在 Tutoia 地层的 3 个区域再开挖 12.4 米。

SJ-06井的总探明(“1P”)石油储量为6.9万桶石油,总探明加概算(“2P”)石油储量为13.4万桶石油。

巴西修井机/服务新闻 >>





原文链接/gulfoilandgas

Petro-Victory Energy Provides Update on Workover Campaign at Sao Joao Field

Source: www.gulfoilandgas.com 2/29/2024, Location: South America

Petro-Victory Energy Corp. ("Petro-Victory") (TSXV: VRY) is pleased to provide an update on the workover campaign to increase oil production in the 100% owned São João field in the Barreirinhas Basin of Maranhão, Brazil.

Highlights:
- SJ-01 successfully completed ahead of schedule and under budget adding an additional 32.2 meters of oil pay in the Tutoia formation.
- SJ-01 initial production rate of 303 barrels of oil per day ("bopd").

- SJ-11 successfully completed on schedule and under budget adding an additional 16 meters of oil pay in the Tutoia formation.
- SJ-11 producing an average of 37 barrels per day with completion fluid still being recovered.
- SJ-06 workover started ahead of schedule with SPT-129 workover rig on location.

SJ-01 Well
On February 16th, 2024 the SPT-129 workover rig mobilized from the SJ-11 well to the SJ-01 well with a workover program designed to open an additional 32.2 meters across 5 zones in the Tutoia formation.

Petro-Victory successfully re-entered the well to a depth of 1,963 meters and installed a bridge plug above the previously open and depleted BGARP-E zone which has been open and produced for more than 60 years. The team then logged and subsequently perforated the originally planned 32.2 meters in 5 previously planned zones.

The well was successfully completed ahead of schedule and under budget on February 27th, 2024, with 1 ¼" insert pump, gas anchor and API-160 pump-jack, being re-installed over the well. The SJ-01 well now has 32.2 meters of oil pay zones open in the Tutoia formation. The open zones are clean sandstones exhibiting 21% average porosity.

Specific data for the initial production rates from the SJ-01 well following workover is as follows:

- The SJ-01 well was opened on February 28th, connected to production station with artificial lift support from the pump jack. On the morning of February 29th, the well started flowing naturally at initial rate of 303 bopd.

- The SJ-01 well has total proved ("1P") reserves of 199 thousand barrels of oil and total proved plus probable ("2P") reserves of 303 thousand barrels of oil.

The team continues to monitor well pressure, production rates, fluid separation, recovery of the completion fluid, and associated gas levels.

Initial production results are not necessarily indicative of long-term performance or ultimate recovery.

SJ-11 Well
As previously announced, the SPT-129 workover rig arrived on January 25, 2024 and began the workover campaign at the SJ-11 well to open and test an additional 21.8 meters across 6 zones in the Tutoia formation.

Petro-Victory successfully re-entered the well to a depth of 1,694 meters, logged the well, and subsequently perforated 16 meters in 5 planned zones between 1,400 meters and 1,634 meters depth with oil and associated gas shows confirming expectations that this is a gas driven, oil prolific, formation.

The Tutoia H zone is a 6 meter oil pay zone which has been open and producing for more than 40 years and during the workover, this and other previously opened zones, combined to absorb 1,700 barrels of completion fluid as the team worked to successfully restore circulation in the well with LCM agents and accomplish the engineering program to full extent.

The well was successfully completed on schedule and under budget on February 16, 2024, with 1 ¼" insert pump, gas anchor and API-160 pump-jack, being re-installed over the well. The SJ-11 well now has 45 meters of oil pay zones open in the Tutoia formation. The open zones are clean sandstones. exhibiting 20% average porosity.

Specific data for the initial production from the SJ-11 well following workover is as follows:
- The SJ-11 well averaged 37 barrels of fluid per day for the last 7 days with 37.5 barrels of fluid per day over an initial 60-hour test, with periodic increases to a rate of up to 150 barrels per day, now producing at a rate of 32.7 barrels of fluid per day over the last 48 hours increasing periodically up to 108 barrels of fluid per day.
- Since completion, the SJ-11 well produced 350 barrels of fluid with associated gas. From which, the well has produced 306 barrels of oil to date.
- Oil from the Tutoia formation is a light crude oil with an API gravity of 39.8° at 20° Celsius.
- Initial production showed 100% completion fluid and moving to full oil production (0% completion fluid) with an average of 83% oil production in the last 48 hours.
- 1,656 barrels of completion fluid estimated still to be recovered.

The SJ-11 well has total proved ("1P") reserves of 200 thousand barrels of oil and total proved plus probable ("2P") reserves of 458 thousand barrels of oil.

The team continues to monitor well pressure, recovery of the completion fluid, and associated gas levels. To efficiently manage the reservoir, the pump-jack is currently running at optimum pump frequency, and a 64/64 choke size is being used.

Initial production results are not necessarily indicative of long-term performance or ultimate recovery.

SJ-06 Well
On February 27th, 2024 the SPT-129 workover rig mobilized from the SJ-01 well to the SJ-06 well with a workover program designed to open an additional 12.4 meters across 3 zones in the Tutoia formation.

The SJ-06 well has total proved ("1P") reserves of 69 thousand barrels of oil and total proved plus probable ("2P") reserves of 134 thousand barrels of oil.

Workover Rigs/Services News in Brazil >>