来源:www.gulfoilandgas.com 2024 年 11 月 4 日,地点:欧洲

Trillion Energy International Inc.(“Trillion”或“公司”)很高兴提供 SASB 气田速度管柱安装程序的最新信息。10

月 27 日,压井装置被安置在 Akcakoca-3 井上方,2 3/8 英寸生产油管(“速度管柱”或“S”)通过现有的 4 英寸油管下入井中。该操作于 10 月 29 日完成。整个操作过程中,井内持续流动。

安装 VS 后,Akcakoca-3 产量从大约 2.0 MMcf/d(安装前 27 天的平均产量)增加到 2.6 MMcf/d(安装后前 4 天的平均产量)。我们目前继续监测井的产量。

2024 年 10 月 30 日,使用压井装置将 2 3/8 速度管柱下入西阿克恰科卡 1 井。该作业于 11 月 1 日完成,速度管柱的总测量深度 (MD) 为 3,496 米。西阿克恰科卡 1 井在作业前没有生产,预计在应用氮气刺激后将恢复天然气生产。

目前,VS 正在下入 Guluc-2 井。安装速度管柱的目的是减少 SASB 气井的水负​​荷问题。

土耳其钻井工程与设备系统新闻 >>





原文链接/GulfOilandGas

Trillion Provides Update on VS Installation

Source: www.gulfoilandgas.com 11/4/2024, Location: Europe

Trillion Energy International Inc. (“Trillion”, or the “Company”) is pleased to provide an update on the velocity string installation program at the SASB gas field.

On October 27th the snubbing unit was positioned over the Akcakoca-3 well where 2 3/8” production tubing (“velocity string” or “VS”) was ran into the well through the existing 4 ½ tubing. The operation was completed on October 29th. The well continued to flow throughout the operation.

Following the VS installation, Akcakoca-3 production increased from approximately 2.0 MMcf/d (average production for the 27 days prior to installation) to 2.6 MMcf/d (average production first 4 days post VS). We continue to monitor production from the well at this time.

On October 30th, 2024 a 2 3/8th velocity string was ran into the West Akcakoca-1 well using the snubbing unit. The operation was completed by November 1st , where the velocity string reached a total measured depth (MD) of 3,496 meters. The West Akcakoca-1 well was not producing prior to the operation and gas production is expected to resume following nitrogen stimulation being applied.

Currently, VS is being run into the Guluc-2 well. The velocity strings are being installed with the objective of reducing water loading issues in the SASB gas wells.