(WO) “澳大利亚 Santos Ltd. 在其季度报告中宣布,预计其 Pikka 项目将于 2026 年首次生产石油。

据桑托斯报道,位于阿拉斯加北坡的 Pikka 项目“在阿拉斯加的冬季取得了出色的进展”。根据声明,截至 2024 年 3 月 31 日,Pikka 项目已完成 47%。本季度完成了 7 口井的钻机作业。已增产4口井,其中3口成功返排。

返排结果优于钻前预期。管道垂直支撑构件已完成 65% 以上,管道铺设已完成 61% 以上,以实现冬季目标。截至本季度末,海水处理厂已完成 62%。

桑托斯于2022年8月对Pikka项目做出了最终投资决定。Pikka项目包括一个钻井场地、一个石油加工设施和其他基础设施,产量预计将达到80,000桶/天。

Pikka 以及该公司的 Barossa 天然气项目和 CCS 合资企业都是“世界级项目,将为桑托斯带来变革,并为该公司至少在未来 10-15 年提供长期、稳定的现金流” ”桑托斯董事总经理兼首席执行官凯文·加拉格尔 (Kevin Gallagher) 说道。

“我们 2024 年的重点是继续推动整个业务的严格低成本运营模式以及 Barossa、Pikka 和 Moomba CCS 项目的执行,同时保持强劲的资产负债表,”Gallagher 总结道。

主要图片(来源:路透社)


原文链接/oilandgas360

World Oil


(WO) – In its quarterly report, Australia’s Santos Ltd. announced it expects first oil production from it’s Pikka Project in 2026.

The Pikka project, in Alaska’s North Slope, has made “excellent progress over the winter months in Alaska,” Santos reported. According to the statement, the Pikka Project is 47% complete as of March 31, 2024. Rig operations were completed on seven wells in the quarter. Four wells have been stimulated with three successfully flowed back.

Flow back results compare favorably with pre-drill expectations. Vertical support members for the pipeline are more than 65% complete, and pipelaying was more than 61% complete for the winter season objectives. The seawater treatment plant was 62% complete at the end of the quarter.

Santos reached a final investment decision on the Pikka Project in August 2022. The Pikka Project includes a single drill site, an oil processing facility and other infrastructure, with production expected to reach 80,000 bopd.

Pikka, along with the company’s Barossa gas project and CCS ventures, are “world-class projects that will be transformative for Santos and set the company up with long-term, stable cash flows for the next 10-15 years at least,” said Santos Managing Director and Chief Executive Officer Kevin Gallagher.

“Our focus for 2024 is continuing to drive the disciplined low-cost operating model across the business and the execution of Barossa, Pikka and Moomba CCS projects whilst maintaining a strong balance sheet,” Gallagher concluded.

Lead image (Credit: Reuters)