完成井新闻

Touchstone 公布 Cascadura-4ST2 X 井钻探结果

Touchstone Exploration 公布了其在奥托瓦尔区块的作业更新,包括卡斯卡杜拉-4 号开发井 (Cas-4ST2X) 的钻探结果。卡斯卡杜拉-4ST2 的作业于 8 月 16 日恢复,使用 Star Valley 陆基钻井平台 #205,该井于 9 月 22 日达到总深度 5,896 英尺。卡斯卡杜拉-4ST2X 是卡斯卡杜拉 A 区块钻探的第三口在目标储层内遇到砂体的井。

该井最初计划评估深度约为 6,100 英尺的 Herrera Gr7bc 砂层。然而,在井下部遇到充气砂岩后,循环中断,导致该公司比计划提前结束钻井作业。

在起出过程中,钻柱卡住,尽管进行了大量的恢复工作,但仍无法脱困。该公司选择采用套管和钻柱组合的方式完成该井的生产,以便能够进入钻井过程中发现的含气层段。

虽然无法获取裸眼测井数据,但偏移井数据和实时钻井信息证实该井与 Herrera Gr7bc 砂层相交。

Cascadura-5井的完井作业将立即开始。所有连接设备均已到位,完井后将直接通过Cascadura天然气设施进行测试。Cas-4ST2X井将在设备和服务钻机到位后进行最终完井和连接作业。

B平台作业完成后,钻井平台将移至中央区块卡拉帕尔岭3号(Carapal Ridge-3)作业点,该区块的施工已完成约60%。预计该地点将于10月底做好钻探准备。

原文链接/DrillingContractor
Completing the WellNews

Touchstone delivers Cascadura-4ST2 X well drilling results

Touchstone Exploration provided an operational update on its Ortoire block activities, including drilling results from the Cascadura-4 development well (Cas-4ST2X). Operations at Cascadura-4ST2 resumed on 16 August, using Star Valley land-based drilling rig #205, and the well reached a total depth of 5,896 ft on 22 September. Cascadura-4ST2X represents the third well drilled into the A block of Cascadura to encounter sands within the targeted reservoir.

The well was originally programmed to evaluate the Herrera Gr7bc sands to a depth of approximately 6,100 ft. However, after encountering gas-charged sands in the lower portion of the well, circulation was lost, leading the company to conclude drilling operations earlier than planned.

During the pull-out, the drill string became stuck and despite extensive recovery efforts, could not be freed. The company has elected to complete the well for production using a combination of casing and the drill string, enabling access to the gas-charged intervals identified while drilling.

Although open-hole logs could not be acquired, offset well data and real-time drilling information confirm that the well intersected Herrera Gr7bc sands.

Completion operations on the Cascadura-5 well will begin immediately. All tie-in equipment is on location and the well will be tested directly through the Cascadura natural gas facility following completion. Cas-4ST2X will undergo final completion and tie-in once equipment and a service rig are on site.

Following completion of Pad B operations, the drilling rig will move to the Central block location identified as Carapal Ridge-3, where site construction is approximately 60 percent complete. The location is expected to be drill-ready by the end of October.