Subsea7 获得土耳其近海合同

TPAO 将 Sakarya 油田开发项目第二阶段合同授予 Subsea7。

哈特能源员工

土耳其石油公司 (TPAO) 已向由 Subsea7、Subsea Integration Alliance、OnseSubsea、SLB 和 Saipem 组成的财团授予土耳其海上 Sakarya 油田开发第二阶段的主要合同。

Subsea7 将重大合同定义为 Subsea7 的收入份额超过 7.5 亿美元的合同。

该项目第一阶段涉及利用海底生产系统从 10 口井生产天然气。第二阶段将钻探多达30口新井,这些井将连接到海底生产系统。还将安装一条新管道,用于运输第二阶段抽取的额外天然气。

“萨卡里亚一期的第一批天然气在发现后仅 30 个月就交付了,”非洲、中东和里海副总裁 Franck Louvety 表示。“Subsea7 期待在第二阶段扩大这种关系,并继续为土耳其能源行业的发展做出贡献。”

该合同的项目范围涉及工程、采购、施工和安装(EPCI),将涵盖地下解决方案,包括海底生产系统(SPS)、海底脐带和出油管线(SURF)。该合同还包括额外的 FEED 研究和选项,以进一步扩大工作范围。

Subsea7 目前执行的范围包括约 23 英里的内场出油管线、29 英里的控制脐带缆和水深约 6,500 英尺的相关海底设备的 EPCI。

Sakarya 二期常规天然气开发项目预计将于 2026 年开始生产,并预计于 2032 年达到峰值,天然气产量约为 1,040 MMcf/d。

TPAO 是该油田 100% 的所有者。

原文链接/hartenergy

Subsea7 Awarded Contract Offshore Turkey

TPAO awarded the contract to Subsea7 for Phase 2 of their Sakarya field development project.

Hart Energy Staff

Turkish Petroleum (TPAO) has awarded a consortium of Subsea7, Subsea Integration Alliance, OnseSubsea, SLB and Saipem with a major contract for the second phase of their Sakarya field development offshore Turkey.

Subsea7 defines a major contract as one where Subsea7’s share of revenue is over USD$750 million.

Phase 1 of the project involved the production of natural gas by using the subsea production system from 10 wells. In Phase 2, up to 30 new wells will be drilled, which will be connected to the subsea production system. A new pipeline will also be installed for transporting the additional gas drawn from Phase 2.

“First gas from Sakarya Phase 1 was delivered just 30 months after discovery,” Franck Louvety, Africa, Middle East & Caspian vice president said.  “Subsea7 looks forward to extending this relationship for Phase 2 and continuing our contribution to the development of the energy industry in Türkiye.”

The project scope of the contract, which is for engineering, procurement, construction and installation (EPCI), will cover the subsurface solutions including subsea production systems (SPS), subsea umbilicals and flowlines (SURF).  The contract also includes additional FEED studies and options to further extend the scope of work.

The current scope to be executed by Subsea7 comprises the EPCI of approximately 23 miles of infield flowlines, 29 miles of control umbilicals and associated subsea equipment in water depths of around 6,500 ft.

Production from the Sakarya Phase 2 conventional gas development project is expected to begin in 2026 and is forecast to peak in 2032, to approximately 1,040 MMcf/d of natural gas.

TPAO is the 100% owner of the field.