Europa Oil & Gas 公布截至 2024 年 7 月 31 日的年度最终业绩

来源:www.gulfoilandgas.com 2024 年 10 月 28 日,地点:非洲

Europa Oil & Gas (Holdings) plc 是一家在 AIM 上市、专注于西非、英国和爱尔兰的石油和天然气勘探、开发和生产的公司,该公司宣布了截至 2024 年 7 月 31 日的 12 个月的最终审计结果。

完整的年度报告和账目将很快在公司网站 www.europaoil.com 上发布,并将邮寄给那些要求获得纸质副本的股东。

财务表现
— 收入下降 46% 至 360 万英镑,反映出石油产量下降(其中包括 Wressle 的三个月停产期)和实际油价下降(2023 年:670 万英镑)
— 毛利 30 万英镑(2023 年:340 万英镑)
— 扣除非现金勘探减值损失 500 万英镑后税前亏损 680 万英镑(2023 年:扣除非现金减值损失 170 万英镑后税前亏损 90 万英镑)
— 经营活动所用净现金 60 万英镑(2023 年:经营活动产生的净现金 280 万英镑)
— 2024 年 7 月 31 日的现金余额:150 万英镑(2023 年:520 万英镑)

运营亮点 - 建立均衡的勘探和生产资产组合

赤道几内亚
— Europa 宣布2023 年 12 月,Europa 达成了一项开创性交易,收购了 Antler Global Limited(“ntler”)42.9% 的股份,该公司拥有赤道几内亚近海 EG-08 许可证 80% 的工作权益。这产生了一项合资安排
——Europa 同意以 300 万美元的现金认购 Antler 的新普通股,分四期付款,目前已完成

“EG-08 是一个极具前景的许可证,拥有三个可钻探的勘探区,内部估计平均预期资源量为 1.4 万亿立方英尺天然气当量” 。Antler
和我们的技术团队进一步评估了整个区块的地震数据,并确定了额外的勘探潜力,平均预期资源量为 2.1 万亿立方英尺天然气当量”
。Antler 于今年第三季度启动了勘探工作,旨在引入合作伙伴进行钻探,可能在 2025 年
” 。三个主要勘探区中只有一个勘探区可以快速与位于爱尔兰近海以南 9 公里的现有天然气基础设施联系起来

- 在 Slyne 盆地已探明天然气区进行风险较低/回报非常高的基础设施主导勘探”
。许可证 FEL 4/19 包含 Inishkea West 天然气勘探区,该区已被绘制为一个大型四向封闭区,预期资源量 Pmean 为 1.5 万亿立方英尺可采天然气”
。爱尔兰政府批准了 4/19 许可证的延期,将许可证期限延长至 2026 年 1 月 31 日
。许可证延期后,重新开始了一项转让程序,目的是引入合作伙伴协助钻探勘探区
。Inishkea West 位于东南方向约 18 公里处的 Corrib 气田的便捷回接范围内。由于靠近 Corrib 基础设施、已绘制的四向封闭、巨大的潜在资源以及较低的封堵风险,Inishkea West 勘探区已成为 FEL 4/19 许可证的主要勘探目标


由于 Wressle 油田的计划停机和含水量增加,英国陆上“净产量下降 48% 至每天 137 桶石油(“topd”)(2023 年:265 bopd”)”
我们继续推进我们的 Cloughton 资产,以确定是否可以使用现代完井技术获得商业费率,从而可以将 192 BCF(Pmean)的 GIIP 潜力货币化。已经就该地点的条款达成一致,目前已开始获取钻探评估井所需的必要许可证,预计将于 2026 年完成。鉴于距离英国天然气网络较近且储层内天然气质量优良,成功的评估井可以快速上线,取代液化天然气进口并减少全球排放。

在整个期间,Wressle 的产量下降
o 整个期间的平均总产量为 357 桶/天(2023 年:710 桶/天),Europa 的净份额相当于 107 桶/天(2023 年:213 桶/天)
o 在 Wressle-1 井上安装了喷射泵,耗时三个月才完成,导致 2023 年 8 月中旬至 11 月初期间生产中断
。在 Wressle 油田进行的一项新的地震解释和测绘工作强调了 Ashover Grit 资源的潜在显着增加以及分析结果现在正被纳入油田开发计划。计划是从现有的 Wressle 现场钻探两口背对背的开发井。该项目于 9 月获得规划许可,但北林肯郡议会授予规划许可的决定随后受到质疑,因为 Finch 最高法院的判决裁定,在规划石油和天然气开发申请时必须考虑范围三排放。预计这将导致规划批准被撤销。Wressle 合资企业现在将提交涵盖潜在范围三排放的更多信息,以便未来的规划流程能够获得批准。一旦获得必要的同意和监管部门批准,将尽快钻探这些井

。除了两口开发井外,目前正在努力通过连接到当地天然气配送网络将从 Wressle 生产的伴生气货币化。这项工作预计将与开发井同时完成,并获得相同的监管部门批准


” ECRE 于 2023 年下半年完成了 Wressle 的修订后的 CPR,其中包含了新的油田解释、历史生产绩效数据和油田开发计划。 CPR 的主要亮点包括:与 2016 年 CPR 相比,2P 储量增加了 263%,将 Penistone Flags 后备资源中的 1,883 mboe 重新归类为 2P 储量,Ashover Grit 和 Wingfield Flags 估计最终可采储量升级 59%,Broughton North 预期资源量升级 23%” 。

全年,Europa 位于英国陆上油田的净产量为 137 桶/天,其中 Wressle 贡献了约 78%,其余来自三个较老的油田。

英国近海 - 北海 Serenity 发现区
。英国政府最近的更迭以及国内监管和财政环境的持续不确定性大大增加了未来石油和天然气行业财政变化的可能性,我们认为这可能对 Serenity 项目的经济效益产生负面影响”

。鉴于 Serenity 许可证将于 9 月底到期2024 年,我们决定让许可证失效,这导致与项目

英国海上许可轮次相关的资本化成本减值 490 万英镑
。2022 年,Europa 参加了英国政府第 33 轮海上石油和天然气许可轮次,2024 年 5 月,北海过渡局 (“STA”) 与公司联系,后者提议 Europa 与另一方达成许可证共享协议,以获得新许可证。

经过仔细考虑,考虑到最近有新的国家加入前景广阔的 EG-08 许可证,并且公司资源有限,公司决定不接受拟议的共享许可证。董事会认为,目前英国新资产的风险/回报主张具有挑战性

董事会
— Simon Oddie 于 2023 年 11 月辞职
— Stephen Williams 于 2023 年 11 月辞职
— Simon Ashby-Rudd 于 2023 年 12 月被任命
— Eleanor Rowley 于 2024 年 4 月被任命

报告期后事件
2024 年 9 月,我们很高兴获得了 Wressle 油田两口新开发井的规划批准,我们预计明年将连续钻探。由于 Finch 最高法院的裁决以及对授予 Wressle 开发下一阶段规划许可的拟议法律挑战,预计法院程序结束后规划许可将被撤销。 Wressle 合资企业计划提交涵盖潜在范围三排放的更多信息,以便未来的规划流程获得批准

”。鉴于英国石油和天然气财政制度的持续不确定性,我们决定不申请延长北海 Serenity 许可证,因为该许可证将于 2024 年 9 月底到期

投资者演示和问答
首席执行官 William Holland、首席运营官 Alastair Stuart 和首席地质学家 Jamie White 将于 2024 年 12 月 2 日星期一为投资者举办在线演示和问答活动。

如需注册参加活动,请访问:
https://www.engageinvestor.com/company/europa-oil-gas-holdings-plc?tab=events&company=follow 会计参考日期变更

公司将立即将其会计参考日期从 7 月 31 日更改为 12 月 31 日。因此,其当前会计期间(开始于 2024 年 8 月 1 日)将于 2025 年 12 月 31 日结束。


由于此项变更,公司即将发布的财务报告日程表将如下:
“2024 年 8 月 1 日至 2024 年 12 月 31 日五个月期间的未经审计中期报告,将于该期间结束后三个月内公布,最迟于 2025 年 3 月 31 日;
”2024 年 8 月 1 日至 2025 年 6 月 30 日十一个月期间的未经审计中期报告,将于该期间结束后三个月内公布,最迟于 2025 年 9 月 30 日;以及
” 发布 2024 年 8 月 1 日至 2025 年 12 月 31 日 17 个月期间的审计报告和账目,并于该期间结束后 6 个月内公布,最迟不晚于 2026 年 6 月 30 日。

Europa 首席执行官 William Holland 表示:
“Europa 在 2023/24 财年宣布了一个非常重要的新国家进入计划,收购了 Antler Global 42.9% 的股份,通过 EG-08 许可证,我们在短期内获得了在赤道几内亚进行勘探的重要机会。 考虑到这个极具前景的碳氢化合物省份提供的奖励规模,我不能过分强调这对 Europa 及其利益相关者来说是多么令人兴奋的机会。 EG-08 拥有超过 2 TCF 的近场、基础设施主导、低风险、振幅与偏移(“VO”)支持的前景,可以快速投入使用,是一项世界级的资产。

我们已建立并运行了一个数据室,并且已经引起了业界的极大兴趣。我们的目标是在未来几个月内完成一项外包工作,同时已开始规划钻井,该井最早可能在明年开钻。

我们全年继续推进爱尔兰业务,并希望将我们 100% 拥有的许可证 FEL 4/19 的一部分外包出去,该许可证包含 1.5 TCF Inishkea West 近场勘探前景。我很高兴地报告,爱尔兰政府已批准延长许可证,许可证期限从 2024 年 1 月延长至 2026 年 1 月 31 日。去年 10 月,我们宣布了内部生成的地震再处理结果,该结果大大改善了前景的地下成像。我们现在对 Inishkea West 的密封和圈闭质量更有信心了。我认为,这种规模和质量的油气储量必须要进行钻探,尤其是因为成功的发现将对爱尔兰未来多年的能源供应安全产生重大影响。

自 2023 年 7 月接管 Cloughton 的运营权以来,我们在 PEDL343(英国陆上许可证)的评估工作方面取得了稳步进展。我们已经就建立钻井平台的场地达成了协议,并已启动规划审批流程,以便在油田上钻一口评估井,以测试是否可以以商业速度生产估计的 192 BCF(Pmean)GIIP。我们认为,虽然英国继续消耗天然气,预计这种情况将持续到 2050 年后,但最负责任的来源是国内天然气,无论是从商业还是环境角度来看。因此,Cloughton 气田的开发完全符合英国政府的英国能源安全战略和 2050 年净零排放目标。

我们继续开发和生产我们在英国陆上的核心资产,并继续投资于我们的旗舰 Wressle 油田。一旦获得必要的批准,我们正在计划开发含气的 Penistone Flags 油藏,使用两个背对背的井。我们相信这些油井将提高石油产量,并将天然气出口到当地电网,从而消除燃烧的需要。

今年,我们的收入为 360 万英镑,虽然这大约是上一年的一半,但我们在 Wressle 油田进行了重大投资,成功安装了喷射泵。喷射泵和相关生产设施的大量工作意味着 Wressle 停产三个月,这对我们生产的石油量产生了重大影响。这一时期的油价下跌进一步加剧了这种情况,导致全年收入减少。尽管如此,我们在年底的 Europa 账户中有 150 万英镑的现金余额,Antler 账户中有 70 万英镑(总额),我们继续从 Wressle 和我们在英国的其他陆上资产中产生现金流。

全年,我们致力于北海中部 Serenity 油田的各种开发方案。然而,随着时间的推移,我们对英国的政治和财政背景越来越担心。我们已经评估了该资产商业化的选项,并且认为在当前环境下,它对 Europa 股东来说并不具有吸引力。因此,在 2024 年 9 月,我们选择不延长 Serenity 许可证,我们认为这符合 Europa 及其股东的最佳利益。

随着我们进入赤道几内亚新国家的预期活动、我们在英国 Cloughton 和 Wressle 的陆上项目以及我们在爱尔兰的土地的进展,我相信我们有能力继续发展公司,我期待在未来 12 个月内向股东通报最新情况。”

赤道几内亚经济/财务分析新闻 >>



挪威 >> 2024 年 11 月 1 日 ——绿色能源和工业开发商 Aker Horizo​​ns ASA 公布了 2024 年第三季度的业绩。Aker Horizo​​ns 的净资本使用率为...
美国 >> 2024 年 11 月 1 日 - 2024 年第三季度 GAAP 净收入为每股 1.12 美元;营业利润(非 GAAP)为每股 0.98 美元
公司缩小了 2024 年全年营业利润预期……


美国 >> 2024 年 11 月 1 日 - 埃克森美孚公司宣布 2024 年第三季度收益为 86 亿美元,假设摊薄,每股收益为 1.92 美元。经营活动产生的现金流为 1.41 亿美元,每股收益为 1.42 美元。
澳大利亚 >> 2024 年 10 月 31 日 - 亮点
- 企业/石油生产/开发,昆士兰州
- 9 月 30 日的现金和流动投资资产 106 万美元;零债务。<...





原文链接/GulfOilandGas

Europa Oil & Gas Announces Final results for the year to 31 July 2024

Source: www.gulfoilandgas.com 10/28/2024, Location: Africa

Europa Oil & Gas (Holdings) plc, the AIM traded West Africa, UK and Ireland focused oil and gas exploration, development and production company, announces its final audited results for the 12-month period ended 31 July 2024.

The full Annual Report and Accounts will be available shortly on the Company’s website at www.europaoil.com and will be mailed to those shareholders who have requested a paper copy.

Financial performance
• Revenue declined 46% to £3.6 million, reflecting lower oil production (which included a threemonth shut in period at Wressle) and lower realised oil prices (2023: £6.7 million)
• Gross profit of £0.3 million (2023: £3.4 million)
• Pre-tax loss of £6.8 million after non-cash exploration impairment loss of £5.0 million (2023: pretax loss of £0.9 million after non-cash impairment loss of £1.7 million)
• Net cash used in operating activities £0.6 million (2023: £2.8 million net cash generated by operations)
• Cash balance at 31 July 2024: £1.5 million (2023: £5.2 million)

Operational highlights - Building a balanced portfolio of exploration and production assets

Equatorial Guinea
• Europa announced a ground-breaking deal in December 2023 with the acquisition of a 42.9% stake in Antler Global Limited (“Antler”), which has an 80% working interest in licence EG-08 offshore Equatorial Guinea. This gives rise to a joint venture arrangement
• Europa agreed a US$3 million cash subscription for new ordinary shares in Antler, with the payments being made in four instalments and which has now completed

• EG-08 is a highly prospective licence which has three drill-ready prospects, with internally estimated Mean Prospective Resource of 1.4 TCF of gas equivalent
• Antler and our technical team has further evaluated the seismic data across the block and has identified additional prospectivity, resulting in a Mean Prospective Resource of 2.1 TCF of gas equivalent
• Antler commenced a farm-down process in Q3 this year with a view to bringing in a partner for drilling, potentially in 2025
• A discovery from only one of the three main prospects could be quickly tied back to existing gas infrastructure located 9km to the south

Offshore Ireland - lower risk / very high reward infrastructure-led exploration in proven gas play in the Slyne Basin
• Licence FEL 4/19 contains the Inishkea West gas exploration prospect, which has been mapped as a large four-way closure with a prospective resource Pmean of 1.5 TCF of recoverable gas
• The FEL 4/19 licence extension was granted by the Irish Government, extending the licence term to 31 January 2026
• Following the licence extension, a farm-out process has begun again with the aim of bringing in a partner to assist with the drilling of the prospect
• Inishkea West is within easy tie-back range of the Corrib gas field situated some 18 kilometres to the southeast. This proximity to the Corrib infrastructure, the mapped four-way closure, the large prospective resource, and the reduced seal risk means that the Inishkea West prospect has become the primary exploration target on the FEL 4/19 licence


Onshore UK – net production declined 48% to 137 barrels of oil per day (“bopd”) (2023: 265 bopd) following planned downtime and increased water cut on the Wressle oilfield
• We continue to progress our Cloughton asset to determine if commercial rates can be obtained using modern completion techniques so that the 192 BCF (Pmean) GIIP potential can be monetised. Terms have been agreed for the site and work has now commenced to secure the necessary permits required to drill an appraisal well, expected to be in 2026. Given the proximity to the UK gas network and quality of the natural gas contained within the reservoir, a successful appraisal well could be quickly brought online, displacing LNG imports and reducing global emissions

• Wressle production declined throughout the period
o Gross production averaged 357 bopd throughout the period (2023: 710 bopd), with Europa’s net share equating to 107 bopd (2023: 213 bopd)
o A jet pump was installed on the Wressle-1 well that took three months to complete and resulted in interrupted production between mid-August through to early November 2023
• A new seismic interpretation and mapping exercise across the Wressle field has highlighted a potentially significant increase in resources from the Ashover Grit and the results of the analysis are now being incorporated into the field development plan. The intention is that two back-to-back development wells will be drilled from the existing Wressle site. Planning consent was received for the project in September, however the North Lincolnshire Council’s decision to grant planning permission has subsequently been challenged in light of the Finch Supreme Court judgement which ruled that scope three emissions must be considered in planning applications for oil and gas developments. This is expected to result in the planning approval being rescinded. The Wressle Joint Venture is now going to submit further information that covers potential scope three emissions such that a future planning process could be approved. The wells will be drilled at the earliest opportunity, once the necessary consents and regulatory approvals have been received

• In addition to the two development wells, work is ongoing to monetise the associated gas being produced from Wressle by connecting to a local gas distribution network. This work is expected to be completed around the same time as the development wells and is subject to the same regulatory approvals


• The revised CPR on Wressle was completed in H2 2023 by ECRE which incorporated the new field interpretation, historical production performance data and the field development plan. The key highlights of the CPR included: 263% increase in 2P Reserves compared to 2016 CPR, reclassification of 1,883 mboe in Penistone Flags Contingent Resources to 2P Reserves, 59% upgrade to the Ashover Grit and Wingfield Flags Estimated Ultimate Recoverable and 23% upgrade to Broughton North Prospective Resources

• Total net production of 137 bopd was produced from Europa’s UK onshore fields during the year with Wressle contributing roughly 78% of this and the remainder coming from the three older fields

Offshore UK - Serenity discovery in the North Sea
• The recent change in government in the UK and the continued uncertainty of the domestic regulatory and fiscal environment has sharply increased the possibility of future fiscal changes for the oil and gas industry, which we believe could negatively impact the economics of the Serenity project

• Given that the Serenity licence was due to expire at the end of September 2024, we have therefore taken the decision to allow the licence to lapse, which has resulted in a £4.9 million impairment of the capitalised costs associated with the project

UK offshore licensing round
• In 2022, Europa participated in the UK Government's 33rd offshore oil and gas licensing round and in May 2024 the Company was contacted by the North Sea Transition Authority (the “NSTA”) who proposed a licence-sharing arrangement between Europa and another party for a new licence.

After careful consideration, the Company has decided not to accept the proposed shared licence given the recent new country entry into the highly prospective EG-08 licence and the limited resources of the Company. The Board believes that the risk/reward proposition for new assets in the UK is currently challenging

Board
• Simon Oddie resigned in November 2023
• Stephen Williams resigned in November 2023
• Simon Ashby-Rudd was appointed in December 2023
• Eleanor Rowley was appointed in April 2024

Post reporting period events
• In September 2024, we were delighted that planning approval was awarded for two new development wells on the Wressle field which we expect to drill back-to-back next year. As a result of the Finch Supreme Court ruling and a proposed legal challenge to the granting of planning permission for the next phase of the Wressle development, it is expected that the planning consent will be rescinded once the court process has concluded. The Wressle Joint Venture plan to submit further information that covers potential scope three emissions such that a future planning process could be approved

• We have decided against applying to extend the Serenity licence in the North Sea following its expiry at the end of September 2024 and given the ongoing uncertainties around the oil and gas fiscal regime in the UK

Investor presentation and Q&A
CEO William Holland, COO Alastair Stuart and Chief Geologist Jamie White will be hosting an online presentation and Q&A for investors on Monday, 2 December 2024.

To register for the event, please visit:
https://www.engageinvestor.com/company/europa-oil-gas-holdings-plc?tab=events&company=follow Change of accounting reference date

The Company is changing its accounting reference date from 31 July to 31 December, with immediate effect. Accordingly, its current accounting period, which commenced on 1 August 2024, will now end on 31 December 2025.


As a result of this change, the Company’s forthcoming financial reporting calendar will be as follows:
• Announcement of unaudited interims for the five-month period from 1 August 2024 to 31 December 2024, to be announced within 3 months of the period end, being by no later than 31 March 2025;
• Announcement of unaudited interims for the eleven-month period from 1 August 2024 to 30 June 2025, to be announced within 3 months of the period end, being by no later than by 30 September 2025; and
• Publication of audited report and accounts for the seventeen-month period from 1 August 2024 to 31 December 2025, to be announced within 6 months of the period end, being by no later than by 30 June 2026.

William Holland, CEO of Europa, said:
“Europa announced a highly material new country entrance during the 2023/24 financial year, with the acquisition of a 42.9% stake in Antler Global, providing us with significant near-term exposure to exploration in Equatorial Guinea through the EG-08 licence. I cannot overstate how exciting an opportunity this is for Europa and its stakeholders, given the sheer scale of the prize on offer in this highly prospective hydrocarbon province. With over 2 TCF of nearfield, infrastructure-led, low-risk, Amplitude versus Offset (“AVO”) supported prospects identified which can be quickly brought online, EG-08 is a world-class asset.

We have a data room up and running and have already seen considerable interest from industry. We are targeting completion of a farm-out within the coming months and have concurrently started planning for a well to be drilled, which could spud as early as next year.

We continue to progress our Irish business throughout the year and are hoping to farm-out a portion of our 100% owned licence FEL 4/19, which contains the 1.5 TCF Inishkea West near-field exploration prospect. I am pleased to report that a licence extension was granted by the Irish Government, extending the licence term from January 2024 to 31 January 2026. Last October, we announced the results of our internally generated seismic reprocessing which has materially improved the subsurface imaging of the prospect. We now have much greater confidence in the quality of the seal and trap at Inishkea West. A prospect of this size and quality simply has to be drilled in my opinion, not least because of the significant impact a successful discovery would have on Ireland’s security of energy supply for a number of years.

Since assuming operatorship of Cloughton in July 2023 we have made steady progress with the appraisal work on PEDL343, which is an onshore UK licence. We have agreed terms for a site on which to establish a drilling pad and have initiated the planning approval process in order to drill an appraisal well on the field to test if the estimated 192 BCF (Pmean) GIIP can be produced at commercial rates. We believe that whilst the UK continues to consume gas, which is forecast to continue beyond 2050, that the most responsible source is, both commercially and environmentally, domestic gas. For that reason, a development of the Cloughton gas field is fully aligned with the UK Government’s British Energy Security Strategy and Net Zero 2050 goals.

We continued to develop and produce from our core assets onshore UK, where we continue to invest in our flagship Wressle oilfield. Planning is ongoing to develop the gassy Penistone Flags reservoir with two back-to-back wells as soon as the necessary approvals have been received. We believe that these wells will boost oil production and enable the export of gas into the local network grid, thus eliminating the need for flaring.

In the year, we delivered revenues of £3.6 million, and whilst this was roughly half of the previous year’s, we invested significantly in the Wressle field with the successful installation of a jet pump. The extensive works on the jet pump and associated production facilities meant that Wressle was offline for three months which materially impacted the volume of oil that we produced. This was further exacerbated by lower oil prices during the period, resulting in the reduced revenue for the year. Nevertheless, we ended the year with a cash balance of £1.5 million in Europa accounts, £0.7 million in Antler accounts (gross) and we continue to generate cashflow from Wressle and our other onshore UK assets.

Throughout the year, we worked on various development options for the Serenity oil discovery in the Central North Sea. However, we became increasingly concerned about the political and fiscal backdrop in the UK as time progressed. We have evaluated the options for commercialisation of the asset and do not believe in the current environment it is attractive for Europa shareholders. Consequently, in September 2024 we chose not to extend the Serenity licence, which we believe is in the best interest of Europa and its shareholders.

Following the expected activity from our new-country entry into Equatorial Guinea, progress with our onshore UK projects at Cloughton and Wressle along with our Irish acreage, I believe we are well positioned to continue to grow the Company, and I look forward to updating shareholders over the coming twelve months.”

Economics/Financial Analysis News in Equatorial Guinea >>



Norway >>  11/1/2024 - Aker Horizons ASA, a developer of green energy and industry, announced results for the third quarter 2024. Aker Horizons’ net capital employed stood a...
United States >>  11/1/2024 - Third-quarter 2024 GAAP net income of $1.12 per share; operating earnings (non-GAAP) of $0.98 per share
Company narrows its full-year 2024 operat...


United States >>  11/1/2024 - Exxon Mobil Corporation announced third-quarter 2024 earnings of $8.6 billion, or $1.92 per share assuming dilution. Cash flow from operating activiti...
Australia >>  10/31/2024 - Highlights
- Corporate/Oil Production/ Development, Queensland
- Cash and liquid investment assets at 30 September $1.06 million; nil debt.<...