全球及区域市场新闻

Monumental 提供新西兰修井作业最新情况

Monumental Energy 提供了其与新西兰能源公司合作位于新西兰塔拉纳基盆地的修井 Copper Moki 1 和 2 的最新情况。

所有长周期和关键设备将于 5 月初到位,RIVAL 钻机计划于 2025 年 5 月 12 日开始在一周内移至现场并在 Copper Moki-2 上安装完毕。两口井的修井计划耗时 17 天,届时如果修井成功,两口井将立即恢复生产。

该项目选择Copper Moki-2井作为第一口井,是因为它是两口井中较容易的一口,因为抽油杆已经从井中取出。Copper Moki-1井仍保留有抽油杆,需要更多时间才能同时将油管和抽油杆取出。

Monumental 和 NZEC 正在评估新井的潜在地点,这些地点要么位于目前获准的钻井平台,要么位于 Waihapa 生产设施附近。

原文链接/DrillingContractor
Global and Regional MarketsNews

Monumental provides operational update on New Zealand workover wells

Monumental Energy provided an update on its workover wells, Copper Moki 1 & 2, with New Zealand Energy, located in the Taranaki basin of New Zealand.

All of the long-lead and critical items will be in hand by early May and the RIVAL rig is scheduled to move to the site and set up on Copper Moki-2 in the week commencing 12 May 2025. The program for both wells is scheduled to take 17 days, at which time both wells will immediately be placed back to production if the workovers are successful.

Copper Moki-2 was selected as the first well in the program because it is the easier of the two wells, given that the pump rods have already been retrieved from the well. Copper Moki-1 still has pump rods in place and will require more time to pull the tubing and the rods contemporaneously.

Monumental and NZEC are evaluating potential sites for new wells either on currently permitted pads or near the Waihapa production facility.