Neptune Energy 开始在德国 Adorf Z18 井生产天然气


由《油田技术》编辑助理出版


Neptune Energy 宣布其位于德国西北部 Georgsdorf 市的 Adorf Z18 气井首次投产。

Z18 井位于石炭系地层,预计将使 Adorf 许可的 Neptune 产量增加约 1900 桶油当量/天,达到约 8200 桶油当量/天。

今年早些时候,现场还完成了一座专门处理天然气的加工厂的建设。

Neptune Energy 德国董事总经理 Andreas Scheck 表示:“Adorf 石炭纪油田开发是 Neptune 在德国最有前途的活动之一,体现了我们在这里发展业务的愿望。”

阿多夫气田于2020年发现,第一口井阿多夫Z15于同年投产。第二口井 Adorf Z16 于 2022 年初开始生产。第三口井 Adorf Z17 于 2023 年 6 月将 Neptune 的产量从许可证增加到约 6300 桶油当量/天。

Neptune Energy 拥有 Adorf 石炭系气田 100% 的权益。

在线阅读文章:https://www.oilfieldtechnology.com/drilling-and-product/27072023/neptune-energy-starts-gas-product-at-adorf-z18-well-germany/

 

本文已被标记为以下内容:

石油和天然气新闻


原文链接/oilfieldtechnology

Neptune Energy starts gas production at Adorf Z18 well, Germany

Published by , Editorial Assistant
Oilfield Technology,


Neptune Energy has announced first production from its operated Adorf Z18 gas well, in the municipality of Georgsdorf, North-Western Germany.

The Z18 well - in the Carboniferous formation - is expected to increase Neptune’s production from the Adorf licence by about 1900 boe/d day to around 8200 boe/d.

Construction of a dedicated processing plant at the site for treatment of the gas was also completed earlier this year.

Neptune Energy’s Managing Director in Germany, Andreas Scheck, said: “The Adorf Carboniferous field development is one of Neptune’s most promising activities in Germany and demonstrates our desire to grow the business here.”

The Adorf gas field was discovered in 2020 and the first well, Adorf Z15, was brought into production in the same year. A second well, Adorf Z16, started production at the beginning of 2022. A third well, Adorf Z17 increased Neptune’s production from the licence to around 6300 boe/d in June 2023.

Neptune Energy owns 100% of the Adorf Carboniferous gas field.

Read the article online at: https://www.oilfieldtechnology.com/drilling-and-production/27072023/neptune-energy-starts-gas-production-at-adorf-z18-well-germany/

 

This article has been tagged under the following:

Oil & gas news