Drilling Update Booth Well in L7 Permit Perth Basin
Source: www.gulfoilandgas.com 6/12/2024, Location: Not categorized
The Ventia 106 rig is expected to be released to the L7 Joint Venture in early July and will take
approximately 10 days to mobilise to the Booth-1 location. Expected drilling to commence in mid to
late July 2024.
The Permits’ Joint Venture comprise Triangle [50% & Operator of the L7 permit] , NZO(25%) and
Strike Energy Ltd (ASX: STX: 25%).