Pantheon Resources宣布Dubhe-1油田目标储层评估结果远超钻探前预估

来源:www.gulfoilandgas.com 2025年8月18日,地点:北美

Pantheon Resources plc (AIM:PANR, OTCQX:PTHRF)(简称“Pantheon”)是一家石油天然气公司,致力于开发阿拉斯加北坡管道和交通基础设施附近的科迪亚克(Kodiak)和阿普恩(Ahpun)油田。该公司今日公布了Dubhe-1评价井的勘探结果。Dubhe

-1的主要目标是顶部层位(SMD-B),用于评估已发现的资源量。此外,该井还设计了三个勘探层位(Prince Creek、SMD-C和斜坡扇系统),此前这些层位均未进行过任何资源量估算。测井数据证实了这些层位具有额外的潜在资源潜力。

要点
- Dubhe-1 导孔已成功钻探、测井和取芯,总测量深度 (MD) 为 12,833 英尺,相当于 8,699 英尺的真实垂直深度 (TVD)
- 对主要目标顶部厚度和质量的分析证实,SMD-B 已超出钻探前的预期。该层段烃类柱的总厚度经测量为 565 英尺的真实垂直厚度 (TVT);超出钻探前预期 26%
- Dubhe-1 还在两个勘探目标中发现了额外的含油气层位; SMD-C 和两个斜坡扇体
- 公司计划在 SMD-B 层位钻探并随后进行流量测试计划的侧钻水平井,以完善生产井类型曲线

Dubhe-1 井:第一阶段成果
Dubhe-1 井计划的第一阶段包括一个斜井,用于收集岩心和测井曲线,从而为主要 SMD-B 区域后续侧钻水平井选择最佳着陆区。该井成功达到了计划的 TVD 并实现了所有计划的目标储层穿透目标 - 包括主要目标和勘探目标。Dubhe

-1 已证实在 SMD-B 主要目标层位中存在一个总 TVT 为 565 英尺的含油气柱。这超出钻前估计值(基于管道状态#1 偏移的 450 英尺 TVT)26%,超出钻前估计值的上限(高达 500 英尺 TVT)13%。储层特性与附近的管道状态#1 发现井一致。流动测试后将确定石油、天然气液体和天然气之间的碳氢化合物混合物。


在SMD-C层段和两个斜坡扇体中发现了额外的含油气层。这些层位未包含在Cawley Gillespie & Associates公司估算的Ahpun潜在资源量2.82亿桶和8040亿立方英尺中,因此这些资源量代表着巨大的上升潜力,可以与已建成的Ahpun SMD-B主储层共同开发。

评估分析详情:
初步分析表明,Dubhe-1已钻遇多个含油气层位,深度约为2,143英尺(总深1,085英尺)。除了该井的主要SMD-B目标层段外,该井段还穿透了多个由砂岩和页岩互层组成的储层。

所有层段均采用全套随钻测井(“LWD”)工具和挥发物分析服务(“VAS”)对密封和未密封岩屑样品进行记录。在SMD-B层段,从11,732 - 11,823英尺(垂深8,142 - 8,187英尺)处采集了90英尺岩心,采收率为100%。此外,还采集了井壁岩心,用于辅助测井校准。


综合分析表明,坎帕阶层段内有以下含油气区:
地层:SMD-C
总产油层段(MD 英尺):10,597-10,715
总产油层段(TVD 英尺):7,565-7,625
厚度(TVT 英尺):60

地层:SMD-B(主要目标区)
总产油层段(MD 英尺):11,051-12,162
总产油层段(TVD 英尺):7,795-8,360
厚度(TVT 英尺):565

地层:斜坡扇 1
总产油层段(MD 英尺):12,460-12,530
总产油层段(TVD 英尺):8,510-8,546
厚度(TVT 英尺):36

地层:斜坡扇 2
总产油层段间隔 (MD 英尺): 12,630 - 12,740
总生产间隔 (TVD 英尺): 8,597 - 8650
厚度 (TVT 英尺): 53

除了这些结果之外,在马斯特里赫特阶间隔 (Prince Creek 和 Upper Schrader Bluff Topsets 1 和 3) 中还发现了碳氢化合物,总厚度为 1,158 英尺 TVT,与 Megrez-1 遇到的相同层位一致。初步分析表明储层特性相似,如果需要,将结合 Megrez-1 的数据进行进一步的技术评估和潜在的相关长期开发规划。

未来计划
公司目前正在最终确定井水平段在 SMD-B 层位 565 英尺 TVT 厚段内的最佳位置。预计未来几天将开始钻探该水平段。除了在导向孔中收集的测井曲线、岩心、岩屑和其他数据外,从该水平分支井钻探过程中收集的数据也将进一步整合到分析中。

同时,公司正在分析数据,以优化该分支井的水力增产方案设计。公司还在为这些作业招标几家服务提供商,预计将在未来两个月内就这些事项做出决定。公司将在相关情况公布后发布有关该作业计划的进一步指导意见。


公司将评估从该井以及之前钻探该层位的井收集的大量数据集,其中包括全岩心和井壁岩心、岩屑的VAS分析、随钻测井和电缆测井、用于校准专有三维勘探的地震校验炮以及储层流体分析(“PVT”)。随着公司资本计划转向Ahpun油田开发,这些分析将用于完善动态储层模型并设计永久性生产设施。公司将于2025年9月9日举办网络研讨会,分享Dubhe-1钻井作业的成果,以及对SMD-C和斜坡扇区中发现的额外潜在资源规模的初步见解。

首席开发官Erich Krumanocker表示:
“我们很高兴地宣布Dubhe-1导孔钻探结果取得成功。该井证实了Ahpun油田油气储层的存在和质量,超出了我们钻探前的预期。我们目前正在转向油田开发规划,以支持资本高效的商业化生产。SMD-C和斜坡扇区的优势凸显了我们投资组合中巨大的潜力。”

美国地层评价新闻 >>






原文链接/GulfOilandGas

Pantheon Resources Announces Dubhe-1 Appraisal Well Exceeds Pre-Drill Estimates in Target Reservoir

Source: www.gulfoilandgas.com 8/18/2025, Location: North America

Pantheon Resources plc (AIM:PANR, OTCQX: PTHRF) ("Pantheon"), the oil and gas company developing the Kodiak and Ahpun oil fields near pipeline and transportation infrastructure on Alaska's North Slope, today announces results from the Dubhe-1 appraisal well.

The primary target of Dubhe-1 was the topset horizon (SMD-B), appraising the already discovered resource. Additionally, the well was designed to encounter three further exploration horizons (Prince Creek, SMD-C and the Slope Fan System), none of which have previously had any resource estimate attributed to them. Logs confirm additional prospective resource upside in these horizons.

Key Points
- The Dubhe-1 pilot hole was successfully drilled, logged and cored to a total measured depth ("MD") of 12,833 ft, equivalent to 8,699 ft true vertical depth ("TVD")
- Analysis of the thickness and quality of the primary target topset confirms that the SMD-B has exceeded the upside pre-drill expectations. The gross thickness of the hydrocarbon column in this interval was measured at 565 ft true vertical thickness ("TVT"); exceeding pre-drill expectations by 26%
- Dubhe-1 also encountered additional hydrocarbon bearing horizons in two of the exploration targets; the SMD-C and two Slope Fans
- The Company intends to drill, and subsequently flow test the planned sidetrack lateral in the SMD-B horizon to refine the production well type curve

Dubhe-1 Well: Phase 1 Outcome
The first phase of the Dubhe-1 well programme consisted of a deviated pilot hole to gather cores and logs to select the optimum landing zone for a subsequent lateral sidetrack in the primary SMD-B zone. The well successfully reached the planned TVD and achieved all planned target reservoir penetrations - both primary and exploration objectives.

Dubhe-1 has confirmed a gross 565 ft TVT hydrocarbon bearing column in the SMD-B primary target horizon. This exceeds the pre-drill estimate (450 ft TVT based on Pipeline State#1 offset) by 26% and the upper end of pre-drill estimates (up to 500 ft TVT) by 13%. Reservoir properties are consistent with the nearby Pipeline State #1 discovery well. The hydrocarbon mix between oil, NGLs and gas will be determined after flow testing.


Additional hydrocarbon bearing zones were encountered in the SMD-C and two Slope Fans. These horizons were not included in the Ahpun estimated contingent resources of 282 million barrels and 804 billion cubic feet, prepared by Cawley Gillespie & Associates and therefore these resources represent material upside potential as co-development opportunities alongside the established Ahpun SMD-B primary reservoir.

Details of Appraisal Analysis
Preliminary analysis indicates that Dubhe-1 has intersected multiple hydrocarbon bearing horizons over approximately 2,143 ft MD (1,085 ft TVT). In addition to the primary SMD-B objective of the well, multiple reservoirs were penetrated in this overall section consisting of interbedded sands and shales.

All intervals were logged with a full suite of Logging While Drilling ("LWD") tools and Volatiles Analysis Service ("VAS") of both sealed and unsealed cuttings samples. A 90 ft core, with 100% recovery, was taken from 11,732 - 11,823 ft MD (8,142 - 8,187 ft TVD) within SMD-B interval. In addition, sidewall cores were gathered to aid with log calibration.


Integrated analysis indicates the following hydrocarbon bearing zones within the Campanian interval:
Formation: SMD-C
Gross Pay Interval (MD ft): 10,597- 10,715
Gross Pay Interval (TVD ft): 7,565 - 7,625
Thickness (TVT ft): 60

Formation: SMD-B (primary target objective)
Gross Pay Interval (MD ft): 11,051 - 12,162
Gross Pay Interval (TVD ft): 7,795 - 8,360
Thickness (TVT ft): 565

Formation: Slope Fan 1
Gross Pay Interval (MD ft): 12,460 - 12,530
Gross Pay Interval (TVD ft): 8,510 - 8,546
Thickness (TVT ft): 36

Formation: Slope Fan 2
Gross Pay Interval (MD ft): 12,630 - 12,740
Gross Pay Interval (TVD ft): 8,597 - 8650
Thickness (TVT ft): 53

In addition to these results, hydrocarbons were also identified in the Maastrichtian interval (Prince Creek and Upper Schrader Bluff Topsets 1 and 3) with a gross thickness of 1,158 ft TVT, in line with those same horizons encountered in Megrez-1. Preliminary analysis indicates similar reservoir properties and the results will be combined with the data from Megrez-1 for further technical evaluation and potential associated long term development planning if warranted.

Forward Plans
The Company is presently finalising the optimum location to position the lateral section of the well within this thick 565ft TVT section of SMD-B horizon. Drilling of this lateral is expected to commence over the coming days. In addition to the logs, cores, cuttings and other data collected in the pilot hole, data gathered from the drilling of this horizontal lateral will be further integrated into the analysis.

At the same time, the Company is analysing data to optimise the design of hydraulic stimulation plans in the lateral. The Company is also tendering several service providers for these operations and a decision is expected to be made on these matters during the next two months. The Company will issue further guidance on this plan of operations when available.


The Company will be evaluating the large data set gathered from this well and previous wells penetrating these horizons that includes whole core and sidewall cores, VAS analysis of cuttings, LWD and wireline logs, seismic check shots to calibrate the proprietary 3D survey and reservoir fluid analysis ("PVT"). These analyses will be used to refine the dynamic reservoir model and design permanent production facilities as the Company's capital programme transitions to Ahpun field development. The Company will host a webinar on 9th September, 2025 to share the results of the Dubhe-1 drilling operation and preliminary insights into the scale of additional prospective resources encountered in the SMD-C and the Slope Fans.

Erich Krumanocker, Chief Development Officer, said:
"We are delighted to announce the Dubhe-1 pilot hole results as a success. The well confirms the presence and quality of the oil and gas reservoirs in the Ahpun field, exceeding our pre-drill expectations. We are now transitioning toward field development planning in support of capital efficient commercial production. The upside presented by the SMD-C and Slope Fan zones highlights the enormous potential in our portfolio."

Formation Evaluation News in United States >>