Prairie Provident Resources Inc.(“Prairie Provident”或“公司”)(TSX:PPR)很高兴提供其在阿尔伯塔省中部 Michichi 地区的前两口 Basal Quartz 井的最新消息。Prairie

Provident 于 2024 年 10 月 15 日开钻了第一口 Basal Quartz 水平井 102/03-19-030-18W4。经过九天的钻井作业后,该井于 2024 年 11 月 9 日通过压裂刺激并通过生产测试设施投产,生产的天然气得到保存。这意味着投产周期为 25 天。该井目前正在清理生产,初始 30 天平均产量(“P30”)约为 275 桶/天中质原油和 850 立方英尺/天天然气(415 桶油当量/天)。该井配备了常规人工举升,仍能流动。生产已受到限制,以优化油藏管理。Prairie

Provident 于 2024 年 10 月 25 日开钻了第二口 Basal Quartz 水平井 100/15-32-029-18W4。这口井在七天内钻完,进行了压裂,并于 2024 年 11 月 18 日投产,投产周期为 24 天。自投产以来,生产的天然气量一直保持着稳定。该井正在清理后生产,并通过生产测试设施实现了初始 21 天平均产量,中质原油约 240 桶/天,天然气约 800 立方英尺/天(375 桶油当量/天)。该井配备了常规人工举升,仍能流动。该井的生产也受到限制,以优化油藏管理。由于水平段出现井下机械问题,50 个阶段中的 29 个阶段或 1,325 米总钻井水平段中的 815 米进行了压裂刺激。公司预计,第 32 段的未来加密位置有可能以更高的速率生产,整个 1,400 米水平段都将进行压裂刺激,并有助于提高整体生产率。


Prairie Provident 已调整其 Michichi Basal Quartz 类型曲线,以反映正在实施的审慎油藏管理。该类型曲线显示较低的 IP30 速率,以及更平缓的下降率,因此按 2024 年 12 月 9 日的条带定价,预计回报时间为七个月。102/03-19 和 100/15-32 井现在都通过公司运营的永久设施进行生产,从而可以继续优化两口井的生产率。Prairie

Provident 目前的产量约为 2,800 桶油当量/天。该公司仅在其 Michichi 土地上就已确定了 40 多个 Basal Quartz 潜在钻井机会。这些钻井机会未在 Prairie Provident 储量数据的最新独立评估中预订,自 2023 年 12 月 31 日起生效。公司在 Michichi 的现有已探明未开发储量预订,如 2023 年年末评估所示,主要包括班夫地层石油储量。

测井、射孔、测试 >>

美国测井、射孔、测试新闻 >>



意大利 >> 2024 年 12 月 16 日 ——专注于欧洲天然气和电力项目的投资公司 Prospex Energy plc 非常高兴地报告从流量中实现的流量......
奥地利 >> 2024 年 11 月 12 日 ——ADX Energy Ltd 于 4 日报告了 Welchau-1 发现井 Reifling 地层上部的流动测试初步结果……

德国 >> 2024 年 12 月 9 日 ——MCF Energy Ltd.(“MCF”、“MCF Energy”或“公司”)很高兴提供有关 Reudnitz 气田测试和开发运营的最新信息,我们……
奥地利 >> 2024 年 12 月 4 日 ——MCF Energy Ltd.(“MCF”、“MCF Energy”或“公司”)提供了位于奥地利上奥地利州 ADX-AT-II 许可证中的 Welchau-1 井生产测试的最新情况……




原文链接/GulfOilandGas

Prairie Provident Resources Provides Basal Quartz Drilling Update

Source: www.gulfoilandgas.com 12/18/2024, Location: North America

Prairie Provident Resources Inc. ("Prairie Provident" or the "Company") (TSX:PPR) is pleased to provide an update on its first two Basal Quartz wells in the Michichi area of Central Alberta.

Prairie Provident spud the first Basal Quartz horizontal well, 102/03-19-030-18W4, on October 15, 2024. Following the nine-day drilling operation, the well was fracture stimulated and brought on-stream through production test facilities, with produced natural gas being conserved, on November 9, 2024. This represents an on-stream cycle time of 25 days. The well is currently being produced on cleanup with an initial 30-day average production rate (“IP30”) of approximately 275 bbl/d of medium crude oil and 850 Mcf/d of natural gas (415 boe/d). The well is equipped with conventional artificial lift and is still capable of flowing. Production has been restricted to optimize reservoir management.

Prairie Provident spud the second Basal Quartz horizontal well, 100/15-32-029-18W4, on October 25, 2024. This well was drilled in seven days, fracture stimulated, and brought on-stream on November 18, 2024, representing an on-stream cycle time of 24 days. Produced natural gas volumes have been conserved since the commencement of production. This well is being produced on cleanup and achieved an initial 21-day average production rate of approximately 240 bbl/d of medium crude oil and 800 Mcf/d of natural gas (375 boe/d) through production test facilities. The well is equipped with conventional artificial lift and is still capable of flowing. Production on this well has also been restricted to optimize reservoir management. Due to a downhole mechanical issue in the horizontal lateral, 29 of 50 stages or 815 meters of the 1,325 meters of total drilled lateral were fracture stimulated. The Company expects that future infill locations in section 32 have the potential to produce at higher rates with the full 1,400-meter horizontal lateral leg being fracture stimulated and contributing to overall production rates.


Prairie Provident has adjusted its Michichi Basal Quartz type curve to reflect the prudent reservoir management being practiced. This type curve exhibits a lower IP30 rate, along with a more gradual decline rate, resulting in an estimated payout of seven months at December 9, 2024 strip pricing. Both the 102/03-19 and 100/15-32 wells are now producing through permanent Company-operated facilities, allowing continued optimized production rates from both wells.

Prairie Provident’s current production is approximately 2,800 boe/d. The Company has identified more than 40 Basal Quartz potential drilling opportunities on its Michichi lands alone. These drilling opportunities are not booked in the most recent independent evaluation of Prairie Provident's reserves data, effective December 31, 2023. The Company's existing proved undeveloped reserves bookings at Michichi, as reflected in the 2023 year-end evaluation, consist primarily of Banff formation oil reserves.

Logging, Perforating, Testing >>

Logging, Perforating, Testing News in United States >>



Italy >>  12/16/2024 - Prospex Energy plc the investment company focused on European gas and power projects, is very pleased to report the flow rates achieved from the flow ...
Austria >>  12/11/2024 - ADX Energy Ltd reported the initial results of flow testing of the upper part of the Reifling formation in the Welchau-1 discovery well on the 4th of...

Germany >>  12/9/2024 - MCF Energy Ltd. ("MCF", "MCF Energy" or the "Company") is pleased to provide an update on Reudnitz Gas field testing and development operations and we...
Austria >>  12/4/2024 - MCF Energy Ltd. ("MCF", "MCF Energy" or the "Company") provides an update on production testing at the Welchau-1 well in the ADX-AT-II licence in Uppe...