Aker BP 授予 Munin 夹克采购和建造合同


由《油田技术》编辑助理出版


该公司已授予 Heerema Vlissingen 一份在 Yggdrasil 地区采购和建造 Munin 夹克的合同。

Aker BP 授予 Munin 夹克采购和建造合同

Yggdrasil 固定设施交付项目总监 Peter Kupka 表示:“这是 Yggdrasil 开发的重要合同。通过这个合同,我们已经将所有主要的固定设施合同放置在 Yggdrasil 地区,并且符合我们的执行计划。”

库普卡继续说道:“Eerema Fabrication Group Vlissingen 是一家经验丰富的国际承包商,拥有良好的业绩记录。我很高兴他们将为 Yggdrasil 做出贡献,并期待开始 Munin 夹克的执行阶段。”

夹克合同于5月23日签订。

2025年交付

Munin是位于北海Yggdrasil地区北部的无人生产平台。艾贝尔正在交付上部结构。

Aker Solutions 将负责夹克的详细工程设计。该夹克将在荷兰弗利辛根的 Heerema 工厂制造。夹克采购将于秋季开始,施工将于 2024 年初开始。

Munin 夹克重 5.8 吨。高度为130 m,安装水深为105 m。将使用八根 60 m 的桩将导管架固定在海床上。安装计划于 2025 年进行,Aker BP 已确保 Yggdrasil 地区所有安装的起重能力。

Peter Kupka 评论道:“我们现在已经确定了 Munin 夹克从工程开始到安装的执行计划。Heerema 还将根据 Aker BP 和 Heerema 船舶承包商之间的单独合同负责导管架的安装。所有参与者都做得很好。”

在线阅读文章:https://www.oilfieldtechnology.com/exploration/30052023/aker-bp-awards-procurement-and-construction-contract-for-the-munin-jacket/

原文链接/oilfieldtechnology

Aker BP awards procurement and construction contract for the Munin Jacket

Published by , Editorial Assistant
Oilfield Technology,


The company has awarded Heerema Vlissingen a contract for procurement and construction for the Munin jacket in the Yggdrasil area.

Aker BP awards procurement and construction contract for the Munin Jacket

Peter Kupka, Project Director for fixed facilities deliveries in Yggdrasil, said: “This is an important contract for the Yggdrasil development. With this award we have placed all major fixed facilities contracts in the Yggdrasil area, and we are in line with our execution plan.”

Kupka continued: “Heerema Fabrication Group Vlissingen is an experienced international contractor with a solid track record. I am very pleased that they will contribute to Yggdrasil and look forward to starting the execution phase for the Munin jacket.”

The jacket contract was signed on 23 May.

Delivery in 2025

Munin is an unmanned production platform in the northern part of the Yggdrasil area in the North Sea. Aibel is delivering the topsides.

Aker Solutions will do the detailed engineering of the jacket. The jacket will be fabricated at the Heerema yard in Vlissingen in the Netherlands. Jacket procurement will start in the autumn, and construction is set to start in the beginning of 2024.

The Munin jacket weighs 5.8 t. The height is 130 m, and it will be installed in a water depth of 105 m. Eight piles of 60 m will be used to secure the jacket to the seabed. Installation is planned in 2025, and Aker BP has secured lifting capacity for all the installations in the Yggdrasil area.

Peter Kupka commented: “We have now secured the execution plan for the Munin jacket from start of engineering to installation. Heerema will also be responsible for the installation of the jacket performed under a separate contract between Aker BP and Heerema marine contractors.? Well done to all involved.”

Read the article online at: https://www.oilfieldtechnology.com/exploration/30052023/aker-bp-awards-procurement-and-construction-contract-for-the-munin-jacket/

 