翻新后的 FPSO 前往科特迪瓦近海 Baleine 油田

2023 年 4 月 7 日
Firenze FPSO将使埃尼集团能够启动深水Baleine油田的生产,这是科特迪瓦最大的碳氢化合物发现。

离岸人员

米兰埃尼与PetroCi合作,庆祝Firenze FPSO 驶往科特迪瓦近海的 Baleine 油田。 

FPSO 将使 Baleine 油田启动生产,该油田是科特迪瓦迄今为止最大的碳氢化合物发现地,估计可替代 2.5 Bbbl 石油和 3.3 Tcf 伴生气。Baleine 的开发也将成为非洲第一个净零排放项目(范围 1 和 2)。 

Firenze FPSO抵达科特迪瓦后将 更名为Baleine ,已进行翻新和升级,使其能够处理高达15,000 桶/天的石油和约 25 Mcfd/天的伴​​生气。全部天然气产量将通过新建的出口管道输送到陆上。海底生产系统的安装和完井活动正在进行中,将确保到 2023 年 6 月加速投产。

埃尼公司的分阶段开发模式和快速通道已被证明是有效的,因为该项目将在距 Baleine 1X 发现井不到两年、FID 一年半后开始生产。埃尼集团在 2022 年 12 月获得最终投资决定后,该项目第二阶段的进展迅速,预计将于 2024 年 12 月投产。

Baleine 油田延伸至 CI-101 和 CI-802 区块。埃尼还拥有科特迪瓦深水区其他四个区块的权益:CI-205、CI-501、CI-401 和 CI-801,均由同一合作伙伴 PetroCi Holding 拥有。

2023年7月4日

由 Massterly LinkedIn 提供
由瓦尔德提供
图片由战略海事领英提供
原文链接/offshore_mag

Refurbished FPSO heads to Baleine Field offshore Côte d'Ivoire

April 7, 2023
The Firenze FPSO will allow Eni's production startup of the deepwater Baleine Field, which is the largest hydrocarbon discovery in Côte d'Ivoire.

Offshore staff

MILAN  Eni, in partnership with PetroCi, celebrated the sailaway of the Firenze FPSO to the Baleine Field offshore Côte d'Ivoire.

The FPSO will allow production startup of the Baleine Field, which is the largest hydrocarbon discovery in Côte d'Ivoire to date, with an estimated oil in place of 2.5 Bbbl and 3.3 Tcf of associated gas. The development of Baleine will also be Africa's first net-zero emission project (Scope 1 and 2). 

The Firenze FPSO, that will be renamed Baleine after its arrival in Cote d’Ivoire, has been refurbished and upgraded to allow it to treat up to 15,000 bbl/d of oil and about 25 Mcfd/d of associated gas. The entire gas production will be delivered onshore via a newly built export pipeline. The installation of the subsea production system and well completion campaign are underway and will ensure an accelerated startup of production by June 2023.

Eni's phased development model and fast track have proven to be effective, as the project is set to start production less than two years from the Baleine 1X discovery well and one and a half years after the FID. Eni is already progressing swiftly on Phase 2 of the project forecasting a startup of production by December 2024 after having taken the FID in December 2022.

The Baleine Field extends over blocks CI-101 and CI-802. Eni also owns interests in four other blocks in the Ivorian deepwater: CI-205, CI-501, CI-401, and CI-801, all with the same partner, PetroCi Holding.