北海 Breidablikk 油田于 10 月 20 日开始生产,比原计划提前四个月,且符合预算。该海底油田与 Grane 平台相连,蕴藏着近 2 亿桶可采石油。合作伙伴包括 Equinor(运营商)、Petoro、V挪威能源公司和康菲石油公司。

“Breidablikk 将在预算范围内提前四个月投产,初始产量高于预期。该项目利润丰厚,为市场提供了重要的产量,并将为挪威社会和业主创造巨大价值。近五该项目已经投入了 100 万个工时。我对项目的交付感到自豪,并感谢所有参与人员。”Equinor 负责项目、钻井和采购的执行副总裁 Geir Tungesvik 说道。

当开发和运营计划 (PDO) 于 2020 年 9 月提交时,Breidablikk 计划于 2024 年上半年开始生产,包括 5 口井的预钻和完井。目前,已经钻探了 8 口井,更多井的钻探工作将持续到 2025 年底。

Breidablikk 正在开发中,使用 4 个模板钻探 22 口海底井。海底设施和 Grane 平台之间已经安装了管道和电缆,该平台已经过改造以接收井流。

该项目在挪威产生了重大连锁反应。超过 90% 的合同价值已流向拥有挪威账单地址的供应商。主要供应商包括卑尔根的 Odfjell Drilling、埃格松的 Aker Solutions、桑讷菲尤尔的 Wood Group 以及位于奥康格的 TechnipFMC。

该项目的投资预计略高于 210 亿挪威克朗(2023 年价值)。

“到 2060 年,Breidablikk 可以帮助延长 Grane 油田的生产寿命和约 1000 个与运营相关的就业岗位。通过利用现有的海上和陆上基础设施,这是一项具有成本效益的开发。在高峰期,Breidablikk 预计将发送Equinor 挪威勘探与生产执行副总裁 Kjetil Hove 表示,每天向市场供应高达 55-60 000 桶油当量,主要销往欧洲。

来自 Breidablikk 的石油在 Grane 进行加工,然后通过管道输送到脴ygarden 的 Sture 码头。未来几年,石油将占 Sture 出口量的 15% 左右。新油田将由位于卑尔根 Sandsli 的 Equinor 组织与 Grane 油田一起运营。

在线阅读文章:https://www.oilfieldtechnology.com/drilling-and-product/20102023/breidablikk-comes-on-stream-ahead-of-schedule/

 

本文已被标记为以下内容:

石油和天然气新闻


原文链接/oilfieldtechnology

Breidablikk comes on stream ahead of schedule

Published by , Deputy Editor
Oilfield Technology,


Production from the Breidablikk field in the North Sea started on 20 October, four months ahead of schedule and within budget. Tied back to the Grane platform, the subsea field holds almost 200 million bbl of recoverable oil. The partners are Equinor (operator), Petoro, Vår Energi and ConocoPhillips.

"Breidablikk will come on stream four months ahead of schedule, within budget, and with higher initial production than expected. The project is highly profitable, provides important volumes to the market, and will create great value for Norwegian society and the owners. Nearly five million working hours have gone into the project. I am proud of the project delivery, and would like to thank everyone involved," says Geir Tungesvik, Equinor’s Executive Vice President for Projects, Drilling & Procurement.

When the plan for development and operation (PDO) was submitted in September 2020, production from Breidablikk was scheduled to start in the first half of 2024, with predrilling and completion of five wells. Now, eight wells have already been drilled, and the drilling of additional wells will continue on the field until the end of 2025.

Breidablikk is being developed with 22 subsea wells drilled from four templates. Pipelines and cables have been installed between the subsea facility and the Grane platform, which has been modified to receive the well stream.

The project has had major ripple effects in Norway. More than 90% of the contract value has gone to suppliers with a Norwegian billing address. The main suppliers are Odfjell Drilling in Bergen, Aker Solutions, with large deliveries from Egersund, Wood Group in Sandefjord, and TechnipFMC, from their spoolbase in Orkanger.

Investments in the project are expected to be just over NOK 21 billion (2023 value).

"Breidablikk can help to extend the productive life and the approximately 1000 jobs associated with the operation of the Grane field towards 2060. By utilising existing infrastructure both offshore and onshore, this is a cost-effective development. At peak, Breidablikk is expected to send up to 55 – 60 000 boe to the market daily, mainly to Europe," says Kjetil Hove, Equinor's Executive Vice President for Exploration and Production Norway.

The oil from Breidablikk is processed on Grane and sent ashore by pipeline to the Sture terminal in Øygarden. Oil will account for about 15% of exports from Sture in the years to come. The new field will be operated together with the Grane field by the Equinor organisation at Sandsli in Bergen.