陆上新闻进展

印尼能源公司报告克鲁区块钻前进展

印尼能源公司报告称,其位于苏门答腊岛克鲁区块的两口计划钻井的钻前准备工作进展顺利,预计第一口井的钻探工作将在 60 天内开始。

K-29 和 WK-5 两口井的钻井平台已建成,包括钻杆、钻头和井口装置在内的长周期设备也已交付。PT Bina Mitra Artha 公司被指定为钻井承包商,其 BMA #9 钻机在完成勘察后已前往 K-29 井位。

由于苏门答腊岛发生严重洪灾,原计划用于钻机调动的道路被毁,钻井作业因此推迟了数周。该公司已获得使用另一条主干道的许可,预计钻井作业将连续进行。

原文链接/DrillingContractor
NewsOnshore Advances

Indonesia Energy reports pre-drilling progress at Kruh Block

Indonesia Energy reported pre-drilling progress on two planned wells at its Kruh Block in Sumatra, with drilling at the first well expected to commence within 60 days.

Drilling pads for both wells, designated K-29 and WK-5, have been constructed and long-lead items including drill pipe, drill bits and wellheads have been delivered. PT Bina Mitra Artha was appointed as drilling contractor, with its BMA #9 rig en route to the K-29 well location after inspection was completed.

Drilling was delayed by several weeks after severe flooding in Sumatra destroyed the road originally planned for rig mobilization. The company secured permits to use an alternative main road, and the wells are expected to be drilled back-to-back.