Falcon Oil & Gas Ltd. - Beetaloo 钻井及增产计划更新

来源:www.gulfoilandgas.com 2025年9月29日,地点:未分类

Falcon Oil & Gas Ltd. (TSXV: FO, AIM: FOG) 欣然公布Beetaloo次盆地当前钻探及未来增产计划的最新进展。Falcon Oil & Gas Australia Limited(“Falcon Australia”)的合资伙伴Tamboran (B2) Pty Limited(统称“合资伙伴”)将继续钻探活动。

钻探活动
- 2025年钻探活动的前两口井已完成并下套管,每口井的水平段长3000米(10000英尺)。钻机现在将安装到第三口也是最后一口井上,钻探生产井和水平段。
- 此次钻探活动是Beetaloo次盆地首次实施批量钻探的多井钻探项目,目前一切顺利,符合时间表和预算。
- 计划对 2025 年钻探的其中一口井的整个 3,000 米水平段进行最多 60 级刺激,预计将在 2026 年初进行 30 天的流量测试,然后在开始天然气销售之前关闭,预计天然气销售将于 2026 年中期开始。
- 2026 年第二季度,雨季过后,预计在开始天然气销售之前对其余三口井(包括 2024 年钻探活动的第二口井)进行刺激。
- Shenandoah South 试点项目(“试点项目”)中的所有油井预计将根据与北领地政府(“北领地政府”)签订的天然气销售协议(“北 SA”)交付合同规定的 40 MMcf/d 的产量,但须视天气条件和最终利益相关者的批准而定。
- 如先前宣布,Falcon Australia 已决定将其在 2025 年钻探的三口井的参与权益降至 0%,且不承担任何成本。

其他近期亮点
- BJV 合作伙伴与原住民土地所有者达成协议,以避免燃烧,并获准在三年内出售拟议试点项目中的评估气。随后,北领地政府根据《天然气有效利用法》(BUG) 批准出售评估气。-
耗资 1.4 亿澳元的 Sturt Plateau 压缩设施(“SPCF”)已于本月开工建设,土方工程和打桩工程已完成。Falcon 在 SPCF 的建设中不承担任何成本。

- 北领地首条Beetaloo输油管道也于本月开工,APA集团投资7000万澳元,负责铺设37公里长的Sturt Plateau输油管道。Falcon

首席执行官Philip O'uigley表示:
“很高兴地报告,我们的运营合作伙伴Tamboran Resources正在按计划执行2025年的钻探工作,其中两口井的钻探已达到目标深度,第三口井也即将完工。我们期待在接下来的几个月里提供更多更新,届时将会非常繁忙。”

澳大利亚钻井新闻 >>



澳大利亚 >> 2025 年 9 月 19 日 - 主要亮点:

- 钻探进展顺利,钻孔 JUD001 已完成
- 钻探设备已移至第二个位置并且……

格鲁吉亚 >> 2025年9月19日 - 专注于格鲁吉亚的开发和生产公司Block Energy plc欣然宣布KRT-39ST井开钻。

正如此前宣布的那样……


挪威 >> 2025 年 9 月 19 日 - Equinor 及其合作伙伴 Vør Energi 和 Aker BP 在弗洛拉以西约 130 公里处钻了一口干井。

野猫井 34/8-20 S 正在钻探……

日本 >> 2025 年 9 月 17 日 - 日本石油勘探株式会社 (JAPEX) 宣布已获得经济产业大臣颁发的许可,可以开展石油勘探和生产活动。




原文链接/GulfOilandGas

Falcon Oil & Gas Ltd. - Beetaloo Drilling and Planned Stimulation Update

Source: www.gulfoilandgas.com 9/29/2025, Location: Not categorized

Falcon Oil & Gas Ltd. (TSXV: FO, AIM: FOG) is pleased to give an update on current drilling and future planned stimulation in the Beetaloo Sub-basin. Falcon Oil & Gas Australia Limited’s (“Falcon Australia”) joint venture partner Tamboran (B2) Pty Limited (collectively the “BJV partners”) continues the drilling campaign.

Drilling Campaign
- The first two wells of the 2025 drilling campaign are drilled and cased, each with a 3,000m horizontal section (10,000-foot). The rig will now rig up on the third and final well to drill the production hole and horizontal section.
- The campaign is the first multi-well drilling program implementing batch drilling in the Beetaloo Sub-basin and is currently in line with timeline and budget.
- Up to a 60-stage stimulation across the full 3,000m horizontal section of one of the 2025 drilled wells is planned and is expected to be flow tested for 30 days in early 2026 prior to being shut-in ahead of the commencement of gas sales, which are expected to commence in mid-2026.
- In Q2 2026, following the wet season, the remaining three wells (which includes the second well of the 2024 drilling campaign) are expected to be stimulated ahead of the commencement of gas sales.
- All wells included in the Shenandoah South Pilot Project (“Pilot Project”) are expected to deliver the contracted 40 MMcf/d volume required under the Gas Sales Agreement (“GSA”) with the Northern Territory Government (“NTG”) subject to weather conditions and final stakeholder approvals.
- As previously announced, Falcon Australia opted to reduce its participating interest in the three wells drilled in 2025 to 0%, with no cost exposure.

Other recent highlights
- The BJV partners agreed terms with Native Title Holders to avoid flaring and received consent to sell appraisal gas from the proposed Pilot Project over a three-year period. Subsequently, the Northern Territory Government approved the sale of appraisal gas under the Beneficial Use of Gas (BUG) Legislation.
- The construction of the A$140 million Sturt Plateau Compression Facility (“SPCF”) commenced this month with earthworks and piling completed. Falcon has no cost exposure in the construction of the SPCF.

- Work also commenced this month on the Northern Territory’s first-ever Beetaloo pipeline, with APA Group investing A$70 million to deliver the 37-kilometre Sturt Plateau Pipeline.

Philip O’Quigley, CEO of Falcon commented:
“It’s great to report our operating partner, Tamboran Resources, is executing the 2025 drilling campaign to plan, with the drilling of two wells completed to target depth and the third well advancing towards completion. We look forward to providing further updates over what will be an extremely busy next few months”

Drilling News in Australia >>



Australia >>  9/19/2025 - Key Highlights:

- Drilling progressing well with drill hole JUD001 complete
- Drill equipment moved to second location and...

Georgia >>  9/19/2025 - Block Energy plc, the development and production company focused on Georgia, is pleased to announce the spud of KRT-39ST.

As announced on t...


Norway >>  9/19/2025 - Equinor and its partners Vår Energi and Aker BP have drilled a dry well about 130 kilometres west of Florø.

Wildcat well 34/8-20 S was dril...

Japan >>  9/17/2025 - Japan Petroleum Exploration Co., Ltd. (JAPEX) announces that it has received the license from the Minister of Economy, Trade and Industry to conduct e...