Buccaneer Energy公司计划通过新的注水装置提高Pine Mills电厂的产量。

2025年12月15日

Buccaneer Energy概述了其位于德克萨斯州 Pine Mills 油田 Fouke 地区资产的下一阶段开发计划,在对近期钻探和新收购的邻近区域进行技术审查后,将推进二次采油计划。

该公司计划采用注水法,利用 Turner #1 和 Daniel #1 井作为注水井。这两口井位于产油层下倾边缘,被认为是建立压力支撑和提高长期采收率的最佳选择。Buccaneer 公司在该地区拥有 32.5% 的作业权益。

在派恩米尔斯地区,注水开采技术已经应用了五十多年,通常可以将采收率从原生开采的约15%提高到30%至50%。目前的估计表明,福克注水项目可以额外开采66.7万至100.2万桶石油,而迄今为止原生开采的采收量为33.3851万桶。

在正式开工运营前,Buccaneer公司必须获得德克萨斯州铁路委员会的批准,成立一个包含所有租赁权人和特许权使用费持有人的注水作业单元。该单元的成立及相关设施的建设预计需要长达六个月的时间。

在准备阶段,特纳1号井将恢复生产,在监管和工程工作进行的同时逐步增加产量。注水作业完成后,布坎尼尔公司计划钻探福克4号井,并对阿拉尔1号井进行侧钻。

首席执行官保罗·韦尔奇表示,这一决定标志着在最大化派恩米尔斯油田的长期价值方面迈出了重要一步。“水力注水法在这些油藏中有着良好的应用记录,我们相信特纳1号井和丹尼尔1号井是理想的注水点,能够支持高效的采油方案,”他说道。

随着研发进展,我们将发布更多更新信息。

原文链接/WorldOil

Buccaneer Energy targets higher output at Pine Mills through new waterflood unit

December 15, 2025

Buccaneer Energy has outlined the next phase of development at its Fouke area assets in the Pine Mills field, Texas, moving forward with a secondary recovery program following a technical review of recent drilling and newly acquired offset acreage.

The company plans to implement a waterflood scheme using the Turner #1 and Daniel #1 wells as injection wells. Located at the downdip limits of the productive reservoir, both wells are considered optimal for establishing pressure support and improving long-term recovery. Buccaneer holds a 32.5% working interest in the area.

Waterflooding has been used in the Pine Mills region for more than five decades, typically increasing recovery factors from about 15% under primary production to between 30% and 50%. Current estimates suggest the Fouke waterflood project could unlock between 667,000 and 1,002,000 additional barrels of oil, compared with 333,851 barrels recovered to date under primary production.

Before operations can begin, Buccaneer must secure approval from the Texas Railroad Commission to form a waterflood unit that includes all leaseholders and royalty owners. Establishing the unit and constructing associated facilities is expected to take up to six months.

During this preparation period, the Turner #1 well will be returned to production, adding incremental output while regulatory and engineering work progresses. Once the waterflood is online, Buccaneer plans to drill the Fouke #4 well and sidetrack the Allar #1 well.

CEO Paul Welch said the decision represents a significant step toward maximizing long-term value from Pine Mills. “Waterflooding has a proven track record in these reservoirs, and we believe the Turner #1 and Daniel #1 wells provide ideal injection points to support a highly effective recovery scheme,” he said.

Further updates will be issued as development advances.