? Drilling rig contract signed with Canadian listed Major Drilling Group
to drill and complete the LF-07 production well at the Pilot Well Project
? Larger, more powerful TXD200 drilling rig being utilised for the first
time with an improved and more advanced mud system
? LF-07 expected to spud in the second half of July following the Naadam
festival, Mongolia’s principal annual holiday break
TMK Energy Limited (TMK or the Company) is pleased to announce the signing of a
drilling contract with Major Drilling Group (“Major”) - a large international Canadian listed drilling
company which has successfully drilled the six previous pilot wells for the Gurvantes XXXV Coal
Seam Gas (CSG) Project.
Mr Dougal Ferguson, TMK Energy’s Chief Executive Officer commented:
“We are pleased to continue our excellent working relationship with Major and its
Mongolian team with the signing of this latest drilling contract. Major has continually
demonstrated that it can execute our drilling programs safely, efficiently and cost
effectively and are one of our key service providers in the country.
LF-07 is located up dip from existing wells and therefore well positioned to be an early
producer of gas. It is expected to be our last pilot production well in the current Lucky
Fox pilot well complex and on completion of its drilling, will mark a significant
milestone for the Company.”
2025 Drilling Program
The planned 2025 drilling program consists of one additional pilot production well and up to five
exploration wells in a highly prospective area some 60 kms to the east of Nariin Sukhait. This program
meets the minimum 2025 work program commitment pursuant to the Company’s Production Sharing
Contract.
Lucky Fox 07 (LF-07) will complement the existing six pilot production wells in the Nariin Sukhait area,
which have been successful in significantly reducing the reservoir pressure over the past 24 months
as demonstrated from the results of the recent pressure build up tests on LF-01, LF-02 and LF-03.
The additional production well (LF-07) is located up dip from LF-05 and along strike from LF-01 and
LF-02 and has been selected to infill the pilot project well pattern and optimise data gathering and gas
production rates from the pilot project (see Figure 1). It will also provide valuable information on
whether the pressure drop seen in LF-01 and LF-02, located along strike to the west and east
respectively, is evident at the LF-07 location.
The vertical production wells in the current pilot well project remain the primary focus of the Company
as it seeks to prove commercial gas flows can be achieved from the upper coal seam.
Following the drilling of LF-07, the Company intends to commence its relatively inexpensive, but
potentially high impact 2025 exploration drilling program which will consist of up to five exploration
wells, with a target of adding to its already significant 2C contingent resources in the region.
For the purposes of ASX Listing Rule 15.5, the Board has authorised for this announcement to be