Synergia Energy Announces the Following Update Regarding Its Cambay PSC in India
Source: www.gulfoilandgas.com 11/10/2025, Location: Asia
Synergia Energy Limited ("Synergia"), announces the following update regarding its Cambay PSC (WI: 50%), onshore India.
Workover Operations:
The work over of the Cambay C-64 well has been completed and the sucker rod pump ("SRP") is operational. The well has been cleared of the brine "kill" fluid and has produced an average of 23 bopd over the last 3 days.
The Aakash work over rig was mobilized to the C-72 well; the workover has been completed and an SRP has been installed. The well is being cleared of brine "kill" fluid and stable production levels will be announced in due course.
Following the C-72 work over, the Aakash rig is currently being mobilized to the C-74 well location to conduct a similar work over program which will complete the three well work over campaign.
Drilling Operations:
The C-78 well was drilled in 12 ¼ inch hole size to 603 meters prior to running 9 5/8 inch casing. Drilling has resumed in 8.5 inch hole size.